Backstage Construction Update – November 21 – 27, 2016

This is a construction update for Backstage Condominium, 1 The Esplanade, November 21 – 27, 2016

Porcelain tile installation on the east face of the tower.

Porcelain tile installation on the east face of the tower.


Exterior work at Backstage is making more progress. One the west side of the tower balcony railings are being installed in the centre and north suites. Last week railings were installed up to the 21st floor, weather permitting, work will continue this week. 

On the east side crews have been installing the porcelain tiles at the very top of the tower and will return to the lower areas in about a week, again this work is weather dependent.

Work on the podium continues with an emphasis on the outdoor pool which is now covered to permit work during cold or inclement weather. 

In the interior amenity areas continue to get closer to being finished.  There has been a lot of progress in the steam rooms and finishing in the 6th floor movie room and poker room.

Remaining unoccupied suites continue to have inspections and new residents are moving in as the finished suites are approved for occupancy. 

Please check back here at ltowerconstructioninfo.com for regular updates.


Podium deck work in progress with the outdoor pool tented to permit cold weather work.

Podium deck work in progress with the outdoor pool tented to permit cold weather work.


Monday, November 21

  • Porcelain tile installation at the top of the east tower.
  • Balcony railing installation continues on the west tower.
  • Podium deck work on the outdoor pool under the tent.
  • Finishing work in amenity areas.

Tuesday, November 22

  • Porcelain tile installation at the top of the east tower.
  • Balcony railing installation continues on the west tower.
  • Podium deck work on the outdoor pool under the tent.
  • Finishing work in amenity areas.

Wednesday, November 23

  • Porcelain tile installation at the top of the east tower.
  • Balcony railing installation continues on the west tower.
  • Podium deck work on the outdoor pool under the tent.
  • Finishing work in amenity areas.

Thursday, November 24

  • Porcelain tile installation at the top of the east tower.
  • Balcony railing installation continues on the west tower.
  • Podium deck work on the outdoor pool under the tent.
  • Finishing work in amenity areas.

Friday, November 25

  • Porcelain tile installation at the top of the east tower.
  • Balcony railing installation continues on the west tower.
  • Podium deck work on the outdoor pool under the tent.
  • Finishing work in amenity areas.

Amenity space panelling in progress.

Amenity space panelling in progress.


Saturday, November 26

  • No scheduled work though move-ins are possible.

Sunday, November 27

  • No work on site though move-ins are possible.

south-side-of-the-podium-deck-looking-east

South side of the podium deck looking east.


 

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s

%d bloggers like this: