Backstage Construction Update – November 14 – 20, 2016

This is a construction update for Backstage Condominium, 1 The Esplanade, November 14 – 20, 2016

Backstage west face of the tower November 11.

Backstage west face of the tower November 11.


The past week at Backstage has seen more progress installing porcelain tiles on the east face of the tower.  

On the west side the porcelain tile installation is now complete. This week balcony railings will start being installed.

A tent was set up on the amenity roof deck to permit tiling and finishing work on the outdoor pool during cold weather. 

Interior work this week will see the amenity steam rooms are being worked. Other amenity areas are nearing completion with wall panelling being installed.  Corridor wallpaper has been installed from 2nd floor to the 5th floor with only hallway carpeting remaining to be completed. 

Check back here at ltowerconstructioninfo.com for regular updates.


Roof deck amenity area, showing BBQ hookups and the tent enclosure to permit cold weather work on the outdoor pool.

Roof deck amenity area, showing BBQ hookups and the tent enclosure to permit cold weather work on the outdoor pool.


Monday, November 14

  • Porcelain tile installation on the east tower.
  • Balcony railing installation on the west tower.
  • Podium deck work on the outdoor pool.
  • Finishing work in amenity areas.

Tuesday, November 15

  • Porcelain tile installation on the east tower.
  • Balcony railing installation on the west tower.
  • Podium deck work on the outdoor pool.
  • Finishing work in amenity areas.

Wednesday, November 16

  • Porcelain tile installation on the east tower.
  • Balcony railing installation on the west tower.
  • Podium deck work on the outdoor pool.
  • Finishing work in amenity areas.

Thursday, November 17

  • Porcelain tile installation on the east tower.
  • Balcony railing installation on the west tower.
  • Podium deck work on the outdoor pool.
  • Finishing work in amenity areas.

Friday, November 18

  • Porcelain tile installation on the east tower.
  • Balcony railing installation on the west tower.
  • Podium deck work on the outdoor pool.
  • Finishing work in amenity areas.

Indoor amenity space nearing completion.

Indoor amenity space nearing completion.


Saturday, November 19

  • No scheduled work

Sunday, November 20

  • No work on site.

Gym equipment installed.

Gym equipment installed.


 

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: