Backstage Construction Update – November 28 – December 4, 2016

This is a construction update for Backstage Condominium, 1 The Esplanade, November 28 – December 4, 2016

Work on the podium deck and east tower porcelain tile continues this week.

Work on the podium deck and east tower porcelain tile continues this week.


Work on the podium deck has focussed on completing parging or the application of a thin coat of a cementitious mortar to the pool’s concrete to refine the surface in preparation for waterproofing, which will commence this week. Work also continues on installing the porcelain tiles on the tower’s east face.

Work continues in the indoor amenity areas. Fireplaces are ready to be measured for stone cladding this week. While flooring in the 5th floor party room scheduled to begin in the next week. Steam units for steam rooms are installed and have been enclosed, and ready for tiling this week.
In the lower corridors carpeting is being installed in the corridors on floors 2, 3, 4, 5 and 7. Wallpaper and painting has been completed.
Another round of inspections on unoccupied units has been completed. This week should see more of the remaining unoccupied suites released for occupancy.

Please check back here at ltowerconstructioninfo.com for regular updates.


The pool is being prepared for waterproofing under the protection of the tenting.

The pool is being prepared for waterproofing under the protection of the tenting.


Monday, November 28

  • Porcelain tile installation at the top of the east tower.
  • Balcony railing installation continues on the west tower.
  • Podium deck work on the outdoor pool under the tent.
  • Finishing work in amenity areas.

Tuesday, November 29

  • Porcelain tile installation at the top of the east tower.
  • Balcony railing installation continues on the west tower.
  • Podium deck work on the outdoor pool under the tent.
  • Finishing work in amenity areas.

Wednesday, November 30

  • Porcelain tile installation at the top of the east tower.
  • Balcony railing installation continues on the west tower.
  • Podium deck work on the outdoor pool under the tent.
  • Finishing work in amenity areas.

Thursday, December 1

  • Porcelain tile installation at the top of the east tower.
  • Balcony railing installation continues on the west tower.
  • Podium deck work on the outdoor pool under the tent.
  • Finishing work in amenity areas.

Friday, December 2

  • Porcelain tile installation at the top of the east tower.
  • Balcony railing installation continues on the west tower.
  • Podium deck work on the outdoor pool under the tent.
  • Finishing work in amenity areas.

Hallways on the lower floors are being completed.

Hallways on the lower floors are being completed.


Saturday, December 3

  • No scheduled work though move-ins are possible.

Sunday, December 4

  • No work on site though move-ins are possible.

Amenity room panelling installed

Amenity room panelling installed


 

Backstage Construction Update – November 21 – 27, 2016

This is a construction update for Backstage Condominium, 1 The Esplanade, November 21 – 27, 2016

Porcelain tile installation on the east face of the tower.

Porcelain tile installation on the east face of the tower.


Exterior work at Backstage is making more progress. One the west side of the tower balcony railings are being installed in the centre and north suites. Last week railings were installed up to the 21st floor, weather permitting, work will continue this week. 

On the east side crews have been installing the porcelain tiles at the very top of the tower and will return to the lower areas in about a week, again this work is weather dependent.

Work on the podium continues with an emphasis on the outdoor pool which is now covered to permit work during cold or inclement weather. 

In the interior amenity areas continue to get closer to being finished.  There has been a lot of progress in the steam rooms and finishing in the 6th floor movie room and poker room.

Remaining unoccupied suites continue to have inspections and new residents are moving in as the finished suites are approved for occupancy. 

Please check back here at ltowerconstructioninfo.com for regular updates.


Podium deck work in progress with the outdoor pool tented to permit cold weather work.

Podium deck work in progress with the outdoor pool tented to permit cold weather work.


Monday, November 21

  • Porcelain tile installation at the top of the east tower.
  • Balcony railing installation continues on the west tower.
  • Podium deck work on the outdoor pool under the tent.
  • Finishing work in amenity areas.

Tuesday, November 22

  • Porcelain tile installation at the top of the east tower.
  • Balcony railing installation continues on the west tower.
  • Podium deck work on the outdoor pool under the tent.
  • Finishing work in amenity areas.

Wednesday, November 23

  • Porcelain tile installation at the top of the east tower.
  • Balcony railing installation continues on the west tower.
  • Podium deck work on the outdoor pool under the tent.
  • Finishing work in amenity areas.

Thursday, November 24

  • Porcelain tile installation at the top of the east tower.
  • Balcony railing installation continues on the west tower.
  • Podium deck work on the outdoor pool under the tent.
  • Finishing work in amenity areas.

Friday, November 25

  • Porcelain tile installation at the top of the east tower.
  • Balcony railing installation continues on the west tower.
  • Podium deck work on the outdoor pool under the tent.
  • Finishing work in amenity areas.

Amenity space panelling in progress.

Amenity space panelling in progress.


Saturday, November 26

  • No scheduled work though move-ins are possible.

Sunday, November 27

  • No work on site though move-ins are possible.

south-side-of-the-podium-deck-looking-east

South side of the podium deck looking east.


 

Backstage Construction Update – November 14 – 20, 2016

This is a construction update for Backstage Condominium, 1 The Esplanade, November 14 – 20, 2016

Backstage west face of the tower November 11.

Backstage west face of the tower November 11.


The past week at Backstage has seen more progress installing porcelain tiles on the east face of the tower.  

On the west side the porcelain tile installation is now complete. This week balcony railings will start being installed.

A tent was set up on the amenity roof deck to permit tiling and finishing work on the outdoor pool during cold weather. 

Interior work this week will see the amenity steam rooms are being worked. Other amenity areas are nearing completion with wall panelling being installed.  Corridor wallpaper has been installed from 2nd floor to the 5th floor with only hallway carpeting remaining to be completed. 

Check back here at ltowerconstructioninfo.com for regular updates.


Roof deck amenity area, showing BBQ hookups and the tent enclosure to permit cold weather work on the outdoor pool.

Roof deck amenity area, showing BBQ hookups and the tent enclosure to permit cold weather work on the outdoor pool.


Monday, November 14

  • Porcelain tile installation on the east tower.
  • Balcony railing installation on the west tower.
  • Podium deck work on the outdoor pool.
  • Finishing work in amenity areas.

Tuesday, November 15

  • Porcelain tile installation on the east tower.
  • Balcony railing installation on the west tower.
  • Podium deck work on the outdoor pool.
  • Finishing work in amenity areas.

Wednesday, November 16

  • Porcelain tile installation on the east tower.
  • Balcony railing installation on the west tower.
  • Podium deck work on the outdoor pool.
  • Finishing work in amenity areas.

Thursday, November 17

  • Porcelain tile installation on the east tower.
  • Balcony railing installation on the west tower.
  • Podium deck work on the outdoor pool.
  • Finishing work in amenity areas.

Friday, November 18

  • Porcelain tile installation on the east tower.
  • Balcony railing installation on the west tower.
  • Podium deck work on the outdoor pool.
  • Finishing work in amenity areas.

Indoor amenity space nearing completion.

Indoor amenity space nearing completion.


Saturday, November 19

  • No scheduled work

Sunday, November 20

  • No work on site.

Gym equipment installed.

Gym equipment installed.


 

Backstage Construction Update – November 7 – 13, 2016

This is a construction update for Backstage Condominium, 1 The Esplanade, November 7 – 13, 2016


Backstage condo, podium limetsone cladding.

Backstage condo, podium limetsone cladding.


Some remaining finishing work is being completed at the top of the west side. Crews have started work at the top of the east side of the tower. Once that is complete, then they will come down the east face installing the remaining porcelain tile.

The metal caps on the 5th floor external podium area were completed last week. Work on the pool and preparation for landscaping continues this week. 

Internal work on the amenity rooms is getting close to being finished.  Panels are currently being installed on the 6th floor while the 5th floor wood wall panels were stained last week.

Pre-inspectors for the remaining unoccupied suites are underway in preparation for the Building Inspector to this week.

Check back here at ltowerconstructioninfo.com for regular updates.


Porcelain cladding completed to the top of the building on the west face of the tower.

Porcelain cladding completed to the top of the building on the west face of the tower.


Monday, November 7

  • Tower cladding installation and exterior work on the podium deck.
  • Tiling, flooring and finishing work in amenity areas; finishing unoccupied suites.

Tuesday, November 8

  • Tower cladding installation and exterior work on the podium deck.
  • Tiling, flooring and finishing work in amenity areas; finishing unoccupied suites.

Wednesday, November 9

  • Tower cladding installation and exterior work on the podium deck.
  • Tiling, flooring and finishing work in amenity areas; finishing unoccupied suites.

Thursday, November 10

  • Tower cladding installation and exterior work on the podium deck.
  • Tiling, flooring and finishing work in amenity areas; finishing unoccupied suites.  

Friday, November 11

  • Tower cladding installation and exterior work on the podium deck.
  • Tiling, flooring and finishing work in amenity areas; finishing unoccupied suites. 

Saturday, November 12

  • Interior and exterior work if necessary.
  • On-site housekeeping work TBD.

Sunday, November 13

  • Possible move-ins.

Backstage lobby

Backstage lobby


 

Sony Plaza update November 7 2016

L Tower  8 The Esplanade – Sony Plaza Update – November 7 

Progress continues at the northwest plaza of the Sony Centre with pavers and landscaping elements being installed. As we noted in our last updated, the new public art piece Triptych Dream Ballet by Toronto artist Harley Valentine has been installed and awaits its public reveal. 

Last month also saw the competition of the paving and concrete pour for the sidewalk on the north side of The Esplanade, along the south wall of the Sony Centre and the southeast face of the L Tower. 

Check back here at ltowerconstructioninfo.com for updates.

Triptych: Dream Ballet awaits its reveal at the Sony Centre's northwest plaza.

Triptych: Dream Ballet awaits its reveal at the Sony Centre’s northwest plaza.


Progress continues on the Sony Centre northwest plaza.

Progress continues on the Sony Centre northwest plaza.


The wide sidewalk in the evening light, just east of the L Tower.

The wide sidewalk in the evening light, just east of the L Tower.


 

 