Backstage Construction Update – October 31 – November 6, 2016

This is a construction update for Backstage Condominium, 1 The Esplanade, October 31 – November 6, 2016


podium-deck-amenity-area-outdoor-pool

Podium deck outdoor amenity area – lap pool


Ongoing work on the exterior at Backstage was slowed this past week by less than ideal weather conditions. However, progress has been made on the west side of the tower at roof level.

Interior work progress on finishing the amenity areas. Tile work on the steam rooms has been completed. This coming week crews will be working to install the the steam equipment.  The party rooms are nearing completion and the amenity kitchen has been installed. Crews will  be installing counters and flooring in the coming days. 

There are a handful of unsold suites which crews will be getting ready for inspections this week and next.  

Check back here at ltowerconstructioninfo.com for regular updates.


Looking south from the amenity space at Backstage

Looking south from the amenity space at Backstage


 

Monday, October 31

  • Tower cladding installation and exterior work on the podium deck.
  • Tiling, flooring and finishing work in amenity areas; finishing unoccupied suites.

Tuesday, November 1

  • Tower cladding installation and exterior work on the podium deck.
  • Tiling, flooring and finishing work in amenity areas; finishing unoccupied suites.

Wednesday, November 2

  • Tower cladding installation and exterior work on the podium deck.
  • Tiling, flooring and finishing work in amenity areas; finishing unoccupied suites.

Thursday, November 3

  • Tower cladding installation and exterior work on the podium deck.
  • Tiling, flooring and finishing work in amenity areas; finishing unoccupied suites.  

Friday, November 4

  • Tower cladding installation and exterior work on the podium deck.
  • Tiling, flooring and finishing work in amenity areas; finishing unoccupied suites. 

Saturday, November 5

  • Interior and exterior work as necessary.
  • On-site housekeeping work.

Sunday, November 6

  • Possible move-ins.

Backstage podium limestone (detail)

Backstage podium limestone (detail)


 

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: