Backstage Construction Update – October 17 – 30, 2016
October 24, 2016 Leave a comment
This is a construction update for Backstage Condominium, 1 The Esplanade, October 17 – 30, 2016
Updated October 24
In the past two weeks caulking work on the north face of the Backstage podium has been getting completed.
Several days of strong winds slowed installation of the porcelain tiles the east and west sides of the tower but work continues to progress.
Interior work in the amenity areas is continuing to progress. Wood paneling on the 5th floor is getting stained and the kitchen cabinets have arrived for the party room. In the past two weeks floor finishes have been completed in the 5th floor party room. The 7th floor Steam room tiles have been installed and installation of the 6thfloor wall panels got underway last week.
2 more unoccupied unites were approved for occupancy by City inspectors this past week. The remaining unsold suites are getting being finished for occupancy inspections in the coming weeks.
Check back here at ltowerconstructioninfo.com for regular updates.
Monday, October 17
- Tower cladding installation and exterior work on the podium deck.
- Tiling, flooring and finishing work in amenity areas; finishing unoccupied suites.
Tuesday, October 18
- Tower cladding installation and exterior work on the podium deck.
- Tiling, flooring and finishing work in amenity areas; finishing unoccupied suites.
Wednesday, October 19
- Tower cladding installation and exterior work on the podium deck.
- Tiling, flooring and finishing work in amenity areas; finishing unoccupied suites.
Thursday, October 20
- Tower cladding installation and exterior work on the podium deck.
- Tiling, flooring and finishing work in amenity areas; finishing unoccupied suites.
Friday, October 21
- Tower cladding installation and exterior work on the podium deck.
- Tiling, flooring and finishing work in amenity areas; finishing unoccupied suites.
Saturday, October 22
- Interior and exterior work as necessary.
- On-site housekeeping work.
Monday, October 24
- Tower cladding installation and exterior work on the podium deck.
- Tiling, flooring and finishing work in amenity areas; finishing unoccupied suites.
Tuesday, October 25
- Tower cladding installation and exterior work on the podium deck.
- Tiling, flooring and finishing work in amenity areas; finishing unoccupied suites.
Wednesday, October 26
- Tower cladding installation and exterior work on the podium deck.
- Tiling, flooring and finishing work in amenity areas; finishing unoccupied suites.
Thursday, October 27
- Tower cladding installation and exterior work on the podium deck.
- Tiling, flooring and finishing work in amenity areas; finishing unoccupied suites.
Friday, October 28
- Tower cladding installation and exterior work on the podium deck.
- Tiling, flooring and finishing work in amenity areas; finishing unoccupied suites.
Saturday, October 29
- Interior and exterior work as necessary.
- On-site housekeeping work.