Backstage Construction Update – October 10 – 16, 2016

This is a construction update for Backstage Condominium, 1 The Esplanade, October 10 – 16, 2016


Porcelain tile on the west side of the tower reaching to the top of the building.

Porcelain tile on the west side of the tower reaching to the top of the building.


 

On the east face of the tower porcelain tiles installers were up to the 13th floor last week and will be pressing on up the building this week.  The west face installation is continuing at the top of the building. 

The limestone work on the podium is substantially complete.

The pool on the podium deck is being worked on this week.  Crews are preparing for waterproofing in the next few weeks: testing the surface prior to tile work beginning. Landscapers will begin some preparatory work on the podium deck this week.


7th floor amenity space in progress at Backstage7th floor amenity space in progress at Backstage


Interior amenity work continues.  Finished panels have been installed on the 5th floor and some of the millwork is complete.  All the gym equipment has arrived and is being installed.

There are few suites left to complete.  Crews are working to finishing them and have them ready to hand over by the end of October.


 

Check back here at ltowerconstructioninfo.com for regular updates.


Monday, October 10 – Thanksgiving Holiday – site closed.  

Tuesday, October 11

  • Tower cladding installation and exterior work on the podium deck.
  • Tiling, flooring and finishing work in amenity areas; finishing unoccupied suites.

Installing porcelain tile on the east face of the tower

Installing porcelain tile on the east face of the tower


Wednesday, October 12

  • Tower cladding installation and exterior work on the podium deck.
  • Tiling, flooring and finishing work in amenity areas; finishing unoccupied suites.

Thursday, October 13

  • Tower cladding installation and exterior work on the podium deck.
  • Tiling, flooring and finishing work in amenity areas; finishing unoccupied suites.  

Friday, October 14

  • Tower cladding installation and exterior work on the podium deck.
  • Tiling, flooring and finishing work in amenity areas; finishing unoccupied suites. 

Saturday, October 15

  • Interior and exterior work as necessary.
  • On-site housekeeping work.

Sunday, October 16

  • Possible move-ins.

Backstage podium facing The Esplanade on Friday, October 7

Backstage podium facing The Esplanade on Friday, October 7


 

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: