Backstage Construction Update – October 3 – 9, 2016
October 3, 2016 Leave a comment
This is a construction update for Backstage Condominium, 1 The Esplanade, October 3 – 9, 2016
Construction work on the interior of Backstage has made great progress over the past 2 weeks. 40 unoccupied suites were approved for occupancy by the building inspector. The fourth floor parking level was also inspected and approved. Within the next two weeks residents will be able to use this parking level after remaining clean-up items are addressed.
The 7th floor gym and yoga equipment arrived last Friday and is being set up this coming week. Walls and flooring installation continues on in the 7th floor amenity spaces. Work is also continuing on the 5th and 6th floor amenity spaces and hallways.
The north face of the podium along The Esplanade is now clear of scaffolding. The mast climber has been removed giving a sense of how the building will look once the sidewalk and landscaping is completed in the coming months.
The porcelain tiling on the west face of the tower is complete up to 35th floor. Installation of the porcelain tiles is underway on the east side of the tower and has been completed to the 9th floor. Tile installation is continuing this week. Work also continues on the podium deck. We will have an update on the pool and and outdoor amenity area next week.
Check back here at ltowerconstructioninfo.com for regular updates.
Monday, October 3
- Tower cladding installation and exterior work on the podium deck.
- Tiling, flooring and finishing work in amenity areas; finishing and inspections in unoccupied suites.
Tuesday, October 4
- Tower cladding installation and exterior work on the podium deck.
- Tiling, flooring and finishing work in amenity areas; finishing and inspections in unoccupied suites.
Wednesday, October 5
- Tower cladding installation and exterior work on the podium deck.
- Tiling, flooring and finishing work in amenity areas; finishing and inspections in unoccupied suites.
Thursday, October 6
- Tower cladding installation and exterior work on the podium deck.
- Tiling, flooring and finishing work in amenity areas; finishing and inspections in unoccupied suites.
Friday, October 7
- Tower cladding installation and exterior work on the podium deck.
- Tiling, flooring and finishing work in amenity areas; finishing and inspections in unoccupied suites.
Saturday, October 8
- Interior and exterior work as necessary.
- On-site housekeeping work.
Sunday, October 9
- Possible move-ins.