Backstage Construction Update – October 31 – November 6, 2016
October 31, 2016 Leave a comment
This is a construction update for Backstage Condominium, 1 The Esplanade, October 31 – November 6, 2016
Ongoing work on the exterior at Backstage was slowed this past week by less than ideal weather conditions. However, progress has been made on the west side of the tower at roof level.
Interior work progress on finishing the amenity areas. Tile work on the steam rooms has been completed. This coming week crews will be working to install the the steam equipment. The party rooms are nearing completion and the amenity kitchen has been installed. Crews will be installing counters and flooring in the coming days.
There are a handful of unsold suites which crews will be getting ready for inspections this week and next.
Check back here at ltowerconstructioninfo.com for regular updates.
Monday, October 31
- Tower cladding installation and exterior work on the podium deck.
- Tiling, flooring and finishing work in amenity areas; finishing unoccupied suites.
Tuesday, November 1
- Tower cladding installation and exterior work on the podium deck.
- Tiling, flooring and finishing work in amenity areas; finishing unoccupied suites.
Wednesday, November 2
- Tower cladding installation and exterior work on the podium deck.
- Tiling, flooring and finishing work in amenity areas; finishing unoccupied suites.
Thursday, November 3
- Tower cladding installation and exterior work on the podium deck.
- Tiling, flooring and finishing work in amenity areas; finishing unoccupied suites.
Friday, November 4
- Tower cladding installation and exterior work on the podium deck.
- Tiling, flooring and finishing work in amenity areas; finishing unoccupied suites.
Saturday, November 5
- Interior and exterior work as necessary.
- On-site housekeeping work.
Sunday, November 6
- Possible move-ins.