Backstage Construction Update – September 26 – October 2, 2016

This is a construction update for Backstage Condominium, 1 The Esplanade, September 26 – October 2, 2016


On the Backstage exterior, porcelain tile has reached 35th floor of the west face of the tower with the remaining tilling expected to be complete by the end of this week. Support brackets are almost complete on the east face of the tower.  

The final round caulking for the limestone on the north podium face is in progress, but was slowed by wet weather last Friday. The Mast Climber on the north face of the podium is scheduled is to be removed this week. Finally, the pool on the podium deck is being prepped for tile; this work will be on-going for a few more weeks.


Lap pool is being prepped for tiling on the podium deck.

The pool is being prepped for tiling on the podium deck.


Interior work on the amenity spaces is focussed on:

  • Installing wall finishes on the 5th floor
  • Receiving and and installing gym equipment which is expected to arrive on Friday.
  • Steam rooms in the amenity areas will be waterproofed this week

After inspections were completed, occupancy approval has been received for 27 of the unoccupied suites.  Another round of approvals is expected within the next 2 weeks. New move-ins will be underway soon.

The 4th floor parking level is also expected to receive its approval for use in the coming two weeks.

Please check back at ltowerconstructioninfo.com for regular updates.

Amenity spaces taking shape at Backstage.

Amenity spaces taking shape at Backstage.


Monday, September 26

  • Tower cladding installation and exterior work on the podium deck.
  • Tiling, flooring and finishing work in amenity areas; finishing and inspections in unoccupied suites.  

Tuesday, September 27

  • Tower cladding installation and exterior work on the podium deck.
  • Tiling, flooring and finishing work in amenity areas; finishing and inspections in unoccupied suites.

The finished mail room at Backstage.

The finished mail room at Backstage.


Wednesday, September 28

  • Tower cladding installation and exterior work on the podium deck.
  • Tiling, flooring and finishing work in amenity areas; finishing and inspections in unoccupied suites.

Thursday, September 29

  • Tower cladding installation and exterior work on the podium deck.
  • Tiling, flooring and finishing work in amenity areas; finishing and inspections in unoccupied suites.  

Friday, September 30

  • Tower cladding installation and exterior work on the podium deck.
  • Tiling, flooring and finishing work in amenity areas; finishing and inspections in unoccupied suites. 

One of the last unfinished hallways at Backstage.

One of the last unfinished hallways at Backstage.


Saturday, October 1

  • Interior and exterior work as necessary.
  • On-site housekeeping work.

Sunday, October 2

  • Possible move-ins.

The support brackets on the east face of the tower as seen from the podium deck.

The support brackets on the east face of the tower as seen from the podium deck.


 

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: