Backstage Construction Update – September 12 – 18, 2016

This is a construction update for Backstage Condominium, 1 The Esplanade, September 12 – 18, 2016


Progress continues on the Backstage exterior. The porcelain supports on the east side are up to 30th floor and should reach the top of the building this week.  On the tower’s west side the porcelain cladding was completed to the 28th last week with the aim of completing it this week or early next week. 

Stucco work along the north east elevation, adjacent the “Green P” driveway, will be nearing completion this week. 

On the interior, amenity area finishes are progressing:

  • On the 5th floor amenity space wall panels are going up. 
  • On the 6th floor, bathroom tiles are complete in the guest suites, while and vanity cabinets have arrived and will be installed this week. 
  • Corridor wallpaper has been installed on 7th and 6th floors, and flooring has been completed on the 7th floor.
  • Finished suites that remain unoccupied are going through inspections, getting ready for upcoming move-ins.  

Please check back at ltowerconstructioninfo.com for regular updates.


Work progressing on the south side of the podium deck at Backstage.

Work progressing on the south side of the podium deck at Backstage.


Monday, September 12

  • Tower cladding installation and exterior work on the podium deck.
  • Tiling, flooring and finishing work in unoccupied suites, and amenity areas.  

Tuesday, September 13

  • Tower cladding installation and exterior work on the podium deck.
  • Tiling, flooring and finishing work in unoccupied suites, and amenity areas.  

Kitchen in a podium level unit close to being finished at Backstage.

Kitchen in a podium level unit close to being finished at Backstage.


Wednesday, September 14

  • Tower cladding installation and exterior work on the podium deck.
  • Tiling, flooring and finishing work in unoccupied suites, and amenity areas.  

Thursday, September 15 

  • Tower cladding installation and exterior work on the podium deck.
  • Tiling, flooring and finishing work in unoccupied suites, and amenity areas.  

Friday, September 16

  • Tower cladding installation and exterior work on the podium deck.
  • Tiling, flooring and finishing work in unoccupied suites, and amenity areas.  

Backstage washer and dryer unit in a podium level suite.

Backstage washer and dryer unit in a podium level suite.


Saturday, September 17

  • Limited interior and exterior work as necessary.

Sunday, September 18

  • Possible move-ins.

Detail of completed support brackets for the porcelain cladding on the east side of the tower at Backstage.

Detail of completed supports for the porcelain cladding on the east side of the tower at Backstage.


 

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: