Backstage Construction Update – August 22 – 28, 2016
August 22, 2016 Leave a comment
This is a construction update for Backstage Condominium, 1 The Esplanade, August 22 – 28, 2016
Construction at Backstage this week remains focussed on exterior facades and continuing work on the remaining interior finishes. Work is also progressing on the outdoor amenity space on the podium deck, with piping for the outdoor swimming pool soon to be installed.
On the west side of the tower porcelain tile was completed to 20th floor last week and will be heading up further into the “20s” this week. On the east side of the tower, support brackets for the porcelain tile cladding were completed last week to the 22nd floor. This week crews continue with bracket installation on the east tower in advance of tile installation.
Work on the podium’s limestone cladding progresses on the east side of the building, facing the entrance to the “Green P” parking lot. At grade, facing The Esplanade, work will soon resume to remove the remaining shoring and replace it with waterproofing and permanent fill.
Inside the building crews continue to finish unoccupied suites and the very few unsold suites that remain. Tiling, drywall and painting continue in the interior amenity areas on Levels 7, 6 and 5.
Please check back at ltowerconstructioninfo.com for regular updates.
Monday, August 22
- Tower and podium cladding installation and exterior work on on podium deck.
- Drywall, tiling and finishing work in unoccupied suites, and amenity areas.
Tuesday, August 23
- Tower and podium cladding installation and exterior work on on podium deck.
- Drywall, tiling and finishing work in unoccupied suites, and amenity areas.
Wednesday, August 24
- Tower and podium cladding installation and exterior work on on podium deck.
- Drywall, tiling and finishing work in unoccupied suites, and amenity areas.
Thursday, August 25
- Tower and podium cladding installation and exterior work on on podium deck.
- Drywall, tiling and finishing work in unoccupied suites, and amenity areas.
Friday, August 26
- Tower and podium cladding installation and exterior work on on podium deck.
- Drywall, tiling and finishing work in unoccupied suites, and amenity areas.
Saturday, August 27
- Limited interior and exterior work.
- General Housekeeping
Sunday, August 28
- Possible move-ins.