Backstage Construction Update – August 22 – 28, 2016

This is a construction update for Backstage Condominium, 1 The Esplanade, August 22 – 28, 2016


Construction at Backstage this week remains focussed on exterior facades and continuing work on the remaining interior finishes. Work is also progressing on the outdoor amenity space on the podium deck, with piping for the outdoor swimming pool soon to be installed.

On the west side of the tower porcelain tile was completed to 20th floor last week and will be heading up further into the “20s” this week. On the east side of the tower, support brackets for the porcelain tile cladding were completed last week to the 22nd floor. This week crews continue with bracket installation on the east tower in advance of tile installation.

Work on the podium’s limestone cladding progresses on the east side of the building, facing the entrance to the “Green P” parking lot. At grade, facing The Esplanade, work will soon resume to remove the remaining shoring and replace it with waterproofing and permanent fill.

Inside the building crews continue to finish unoccupied suites and the very few unsold suites that remain. Tiling, drywall and painting continue in the interior amenity areas on Levels 7, 6 and 5.

Please check back at ltowerconstructioninfo.com for regular updates.


The future swmining pool on the podium deck at Backstage

The future swimming pool on the podium deck at Backstage


Monday, August 22

  • Tower and podium cladding installation and exterior work on on podium deck.
  • Drywall, tiling and finishing work in unoccupied suites, and amenity areas.  

Tuesday, August 23

  • Tower and podium cladding installation and exterior work on on podium deck.
  • Drywall, tiling and finishing work in unoccupied suites, and amenity areas.  

Wednesday, August 24

  • Tower and podium cladding installation and exterior work on on podium deck.
  • Drywall, tiling and finishing work in unoccupied suites, and amenity areas.  

Amenity space finishing work at Backstage

Amenity space finishing work at Backstage


Thursday, August 25

  • Tower and podium cladding installation and exterior work on on podium deck.
  • Drywall, tiling and finishing work in unoccupied suites, and amenity areas.  

Friday, August 26

  • Tower and podium cladding installation and exterior work on on podium deck.
  • Drywall, tiling and finishing work in unoccupied suites, and amenity areas.  

Porcelain tile installation on the west side of the tower at Backstage

Porcelain tile installation on the west side of the tower at Backstage


Saturday, August 27

  • Limited interior and exterior work.
  • General Housekeeping 

Sunday, August 28

  • Possible move-ins. 

Installing brackets for porcelain tiling on the east side of the tower at Backstage

Installing brackets for porcelain tiling on the east side of the tower at Backstage

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: