Backstage Construction Update – August 15 – 21, 2016

This is a construction update for Backstage Condominium, 1 The Esplanade, August 15 – 21, 2016

30 days or more of 30 degree heat has taken a toll on the pace of construction at Backstage. Even so work continues on the exterior at a steady pace. On the west side of the tower porcelain tile was completed to 15th floor last week and will be heading up to the “20s” this week. On the east side of the tower, support brackets for the porcelain tile cladding were completed last week to the 17th floor. This week crews aim to complete bracket installation will into the “20s.” 

Work on the podium’s limestone cladding sees steady progress with the emphasis on the east facing wall of the podium.

Inside the building, crews have completed more suites and construction management is continuing to complete inspections prior to the next round of suite occupancyTiling, drywall and painting are continuing this week in the interior amenity areas on Levels 7, 6 and 5.

Please check back at ltowerconstructioninfo.com for regular updates.
Looking west from the podium amenity deck at Backstage

Looking west from the podium amenity deck at Backstage

Monday, August 15

  • Cladding installation and exterior work.
  • Drywall, tiling and finishing work in unoccupied suites, and amenity areas.  

Tuesday, August 16

  • Cladding installation and exterior work.
  • Drywall, tiling and finishing work in unoccupied suites, and amenity areas.  

Wednesday, August 17

  • Cladding installation and exterior work.
  • Drywall, tiling and finishing work in unoccupied suites, and amenity areas.  
Backstage detail of east face cladding on the podium

Backstage detail of east face cladding on the podium

Thursday, August 18

  • Cladding installation and exterior work.
  • Drywall, tiling and finishing work in unoccupied suites, and amenity areas.  

Friday, August 19

  • Cladding installation and exterior work.
  • Drywall, tiling and finishing work in unoccupied suites, and amenity areas.  

Saturday, August 20

  • Limited interior and exterior work.
  • General Housekeeping 

Sunday, August 21

  • Possible move-ins. 
Installing porcelain tiles on the west side of Backstage

Installing porcelain tiles on the west side of Backstage

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: