Backstage Construction Update – July 16 – 24, 2016

This is a construction update for Backstage Condominium, 1 The Esplanade, July 16 – 24, 2016

Backstage construction faced some slight delays in the past week as a result of the heavy rain and extreme heat. To help make up for this, work crews will be coming in earlier within permitted construction work hours.

This week and next prep work for the east side porcelain tile panel-backing continues to progresses with on the east side. Work crews have been measuring and aligning their assemblies to be ready for the final tile installation.

Installation of porcelain tile on the west side of the tower is making steady progress and continues through next week and beyond until the tile reaches the top of the tower fins.

The north face of the podium also continues to progress.  This week and next, crews are installing some of the special cut pieces that will complete the facade.

Other work that is ongoing includes: applying finishes to the balcony floors, and applying finishes to floors on the 7th and 6th amenity levels.

Suite inspections are continuing for the remaining unfinished “Hoist Suites”(east tower), and some of the unfinished suites on the amenity levels (7th and 6th floors). 

Please check back at ltowerconstructioninfo.com for regular updates.

Porcelain tile installation on the west tower face at Backstage

Porcelain tile installation on the west tower face at Backstage

Saturday, July 16

  • Some general housekeeping work on site. 
  • Possible Move-ins 

Sunday, July 17

  • Possible Move-ins 
Finishing work in progress in amenity area at Backstage

Finishing work in progress in amenity area at Backstage

Monday, July 18

  • Cladding installation and exterior work.
  • Drywall and finishing work in unoccupied suites, lobby and amenity areas.  

Tuesday, July 19

  • Cladding installation and exterior work.
  • Drywall and finishing work in unoccupied suites, lobby and amenity areas.  

Wednesday, July 20

  • Cladding installation and exterior work.
  • Drywall and finishing work in unoccupied suites, lobby and amenity areas.  

Thursday, July 21

  • Cladding installation and exterior work.
  • Drywall and finishing work in unoccupied suites, lobby and amenity areas.  

Friday, July 22

  • Cladding installation and exterior work.
  • Drywall and finishing work in unoccupied suites, lobby and amenity areas.  
Hallway finishing on podium level nearing completion at Backstage

Hallway finishing on podium level nearing completion at Backstage

Saturday, July 23

  • Limited interior and exterior work.
  • General Housekeeping 

Sunday, July 24

  • Possible move-ins. 

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: