Backstage Construction Update – July 16 – 24, 2016
July 15, 2016 Leave a comment
This is a construction update for Backstage Condominium, 1 The Esplanade, July 16 – 24, 2016
Backstage construction faced some slight delays in the past week as a result of the heavy rain and extreme heat. To help make up for this, work crews will be coming in earlier within permitted construction work hours.
This week and next prep work for the east side porcelain tile panel-backing continues to progresses with on the east side. Work crews have been measuring and aligning their assemblies to be ready for the final tile installation.
Installation of porcelain tile on the west side of the tower is making steady progress and continues through next week and beyond until the tile reaches the top of the tower fins.
The north face of the podium also continues to progress. This week and next, crews are installing some of the special cut pieces that will complete the facade.
Other work that is ongoing includes: applying finishes to the balcony floors, and applying finishes to floors on the 7th and 6th amenity levels.
Suite inspections are continuing for the remaining unfinished “Hoist Suites”(east tower), and some of the unfinished suites on the amenity levels (7th and 6th floors).
Please check back at ltowerconstructioninfo.com for regular updates.
Saturday, July 16
- Some general housekeeping work on site.
- Possible Move-ins
Sunday, July 17
- Possible Move-ins
Monday, July 18
- Cladding installation and exterior work.
- Drywall and finishing work in unoccupied suites, lobby and amenity areas.
Tuesday, July 19
- Cladding installation and exterior work.
- Drywall and finishing work in unoccupied suites, lobby and amenity areas.
Wednesday, July 20
- Cladding installation and exterior work.
- Drywall and finishing work in unoccupied suites, lobby and amenity areas.
Thursday, July 21
- Cladding installation and exterior work.
- Drywall and finishing work in unoccupied suites, lobby and amenity areas.
Friday, July 22
- Cladding installation and exterior work.
- Drywall and finishing work in unoccupied suites, lobby and amenity areas.
Saturday, July 23
- Limited interior and exterior work.
- General Housekeeping
Sunday, July 24
- Possible move-ins.