Backstage Construction Update – July 9 – 15, 2016

This is a construction update for Backstage Condominium, 1 The Esplanade, July 9 – 15, 2016

This week and next the mast climber on the east side of the tower is being completed. Installation of porcelain tile on the east side will commence this coming week.  Rain on July 7 and 8 slowed down work on the installation of limestone and stucco cladding on the podium and porcelain tile on the west side of the tower. The construction management team expects exterior work to pick up, depending on weather conditions, next week. 

The next round of suites are being readied for inspections over the next week. There will be more occupancies over the next 10 days, so move-ins are expected over the weekend and next week.

Work on the main lobby is progressing. The installation of mirror wall framing is on the ground floor is now complete and the backing is being installed over the next few days.

Please check back at ltowerconstructioninfo.com for regular updates.

Backstage podium deck looking west

Backstage podium deck looking west

Saturday, July 9

  • Some general housekeeping work on site. 
  • Possible Move-ins 

Sunday, July 10

  • Possible Move-ins 
Backstage Podium Limestone installation

Backstage Podium Limestone installation

Monday, July 11

  • Cladding installation and exterior work.
  • Drywall and finishing work in unoccupied suites, lobby and amenity areas.  

Tuesday, July 12

  • Cladding installation and exterior work.
  • Drywall and finishing work in unoccupied suites, lobby and amenity areas.  

Wednesday, July 13

  • Cladding installation and exterior work.
  • Drywall and finishing work in unoccupied suites, lobby and amenity areas.  

Thursday, July 14

  • Cladding installation and exterior work.
  • Drywall and finishing work in unoccupied suites, lobby and amenity areas.  

Friday, July 15

  • Cladding installation and exterior work.
  • Drywall and finishing work in unoccupied suites, lobby and amenity areas.  
East side podium cladding in progress (detail)

East side podium cladding in progress (detail)

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: