Backstage Construction Update – July 25 – August 1, 2016
July 25, 2016 Leave a comment
This is a construction update for Backstage Condominium, 1 The Esplanade, July 25 – August 1, 2016
The installation of porcelain tile on the west tower fins reached the 9th floor last week and will continue moving up the tower this week. Crews are continuing to place brackets and insulation on the east side of the tower. Caulking is underway on the north face of the podium.
Glass and frames are began being replaced at the south east corner of the 5th and 6th floors last week and will continue this week. This repairs areas of minor damage from the winter podium deck fire. This work will take 2 weeks to complete.
This week crews will be moving the equipment from the west side to the east, near Green P entrance and commence working to install limestone cladding on that face of the podium.
Inside the building amenity areas are being finished; tiles are being installed in the washrooms and change rooms for the pool.
The next round of suites are getting prepared for move-ins with a new round of inspections scheduled to be completed in the coming week.
Please check back at ltowerconstructioninfo.com for regular updates.
Monday, July 25
- Cladding installation and exterior work.
- Drywall, tiling and finishing work in unoccupied suites, lobby and amenity areas.
Tuesday, July 26
- Cladding installation and exterior work.
- Drywall, tiling and finishing work in unoccupied suites, lobby and amenity areas.
Wednesday, July 27
- Cladding installation and exterior work.
- Drywall, tiling and finishing work in unoccupied suites, lobby and amenity areas.
Thursday, July 28
- Cladding installation and exterior work.
- Drywall, tiling and finishing work in unoccupied suites, lobby and amenity areas.
Friday, July 29
- Cladding installation and exterior work.
- Drywall, tiling and finishing work in unoccupied suites, lobby and amenity areas.
Saturday, July 30
- Limited interior and exterior work.
- General Housekeeping
Sunday, July 31
- Possible move-ins.
Monday, August 1 – Civic Holiday – Site Closed.