Backstage Construction Update – July 2 – 8, 2016

This is a construction update for Backstage Condominium, 1 The Esplanade, July 2 – 8, 2016

The installation of the exterior finishes on the tower fins and podium is proceeding well. 

The installation of the mast climber on the east side of the tower is almost completed and the crew responsible for the installation of the substrate for the porcelain tile on the west side will be moving to the east side. A second crew will be added to carry on with installation of the porcelain tile on the west side.

There will be a mobilization of a Toro Aluminum crew on site next week to remove and replace the damaged frames and glass on the southeast corner on the podium caused by the January fire. This process will take a few weeks.

Suites though-out are being readied for inspections next week and the next phase of occupancies take place the week of July 11th ( a total of 26).

Work is also being carried out in the main lobby to prepare for the installation of the mirror detail on the north side of the lobby.

Please check back at ltowerconstructioninfo.com for regular updates.

Surfacing and waterproofing work continues on the podium deck.

Surfacing and waterproofing work continues on the podium deck.

Friday, July 1 – Canada Day

NOTE: While there will be no work on site there may be residential move-ins. 

Saturday, July 2

  • Some general housekeeping work on site. 
  • Possible Move-ins 

Sunday, July 3

  • Possible Move-ins 
Support struts in the parking garage for the east tower mast climber

Support struts in the parking garage for the east tower mast climber

Monday, July 4

  • Cladding installation and exterior work.
  • Drywall and finishing work in unoccupied suites, lobby and amenity areas.  
  • Toro Aluminum doing repair working on-site. 

Tuesday, July 5

  • Cladding installation and exterior work.
  • Drywall and finishing work in unoccupied suites, lobby and amenity areas.  
  • Toro Aluminum doing repair working on-site.

Wednesday, July 6

  • Cladding installation and exterior work.
  • Drywall and finishing work in unoccupied suites, lobby and amenity areas.  
  • Toro Aluminum doing repair working on-site.
Completed third floor garage at Backstage

Completed third floor garage at Backstage

Thursday, July 7

  • Cladding installation and exterior work.
  • Drywall and finishing work in unoccupied suites, lobby and amenity areas.  
  • Toro Aluminum doing repair working on-site.

Friday, July 8

  • Cladding installation and exterior work.
  • Drywall and finishing work in unoccupied suites, lobby and amenity areas.  
  • Toro Aluminum doing repair working on-site.
East face of the Backstage podium

East face of the Backstage podium

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: