Backstage Construction Update – June 25 – July 1, 2016
June 24, 2016 Leave a comment
This is a construction update for Backstage Condominium, 1 The Esplanade, June 25 – July 1, 2016
Exterior work at the backstage takes another step forward as a tower hoist or mast climber is being built on the east side of the tower in preparation for the installation of porcelain panels on the fins. Porcelain tile installation continues on the west side of the tower and is now up to approx. the 7th floor. Stucco work is underway and continues this week on the northeast side of the podium.
The outdoor amenity space on the podium deck is being waterproofed and its surface is being prepared for the installation of pavers and landscaping.
Interior work this week sees the return of drywallers and related trades permitting work to resume in the unfinished amenity areas and the lower suites.
Residents have started parking on the first 3 levels that were opened up last week.
Please check back at ltowerconstructioninfo.com for regular updates.
Saturday, June 25
- General housekeeping work on site.
Monday, June 27
- Cladding installation and exterior work.
- Drywall and finishing work in unoccupied suites, lobby and amenity areas.
Tuesday, June 28
- Cladding installation and exterior work.
- Drywall and finishing work in unoccupied suites, lobby and amenity areas.
Wednesday, June 29
- Cladding installation and exterior work.
- Drywall and finishing work in unoccupied suites, lobby and amenity areas.
Thursday, June 30
- Cladding installation and exterior work.
- Drywall and finishing work in unoccupied suites, lobby and amenity areas.
Friday, July 1st – site closed for CANADA DAY