L Tower update June 1 – 10
June 3, 2016 Leave a comment
L Tower construction information 8 The Esplanade – L Tower – June 1 – 10
Since the L tower crane was successfully removed on May 18th work continues to prepare for the in the final phases of remaining exterior work, including window glazing where the support struts for the crane connected to the tower and at street level. Check back here at ltowerconstructioninfo.com for regular updates.
- Windows will be installed in the areas where the strut supports for the crane had been attached to the building.
- Sidewalk work will follow once all exterior tower work is completed.
- The maintenance platform on the top floor will be completed in the coming weeks.
- The NW plaza at the Sony Centre will continue to worked on and is set to open later this year.

L Tower at grade, where future sidewalk work will occur now that the crane has been removed, May 27 2016