Backstage Construction Update – June 4 – 10, 2016
June 3, 2016 Leave a comment
This is a construction update for Backstage Condominium, 1 The Esplanade, June 4 – 10, 2016
Work at Backstage continues to progress at a steady pace. On the north face of the podium construction workers are caulking the stone joints. On the west face of the tower work is ongoing to prepare for the installation of the porcelain tile that will clad the “fins” that rise the full height of the building.
The ongoing labour disruption in key trades, such as drywallers, continues to slow finishing work for suites that were not completed prior to strike action commencing.
There is ongoing preparation and testing for the parking levels. Crews have worked with City of Toronto staff to complete some of the key tests. Formal inspections for the parking levels are expected to be completed by mid-June.
Please check back at ltowerconstructioninfo.com for regular updates.
Saturday, June 4
- Possible move-ins.
- General housekeeping work on site.
Monday, June 6
- Cladding installation and exterior work.
- Interior work on the parking levels.
Tuesday, May 7
- Cladding installation and exterior work.
- Interior work on the parking levels.
Wednesday, June 8
- Cladding installation and exterior work.
- Interior work on the parking levels
Thursday, June 9
- Cladding installation and exterior work.
- Interior work on the parking levels
Friday, June 10
- Cladding installation and exterior work.
- Interior work on the parking levels