Backstage Construction Update – July 2 – 8, 2016

This is a construction update for Backstage Condominium, 1 The Esplanade, July 2 – 8, 2016

The installation of the exterior finishes on the tower fins and podium is proceeding well. 

The installation of the mast climber on the east side of the tower is almost completed and the crew responsible for the installation of the substrate for the porcelain tile on the west side will be moving to the east side. A second crew will be added to carry on with installation of the porcelain tile on the west side.

There will be a mobilization of a Toro Aluminum crew on site next week to remove and replace the damaged frames and glass on the southeast corner on the podium caused by the January fire. This process will take a few weeks.

Suites though-out are being readied for inspections next week and the next phase of occupancies take place the week of July 11th ( a total of 26).

Work is also being carried out in the main lobby to prepare for the installation of the mirror detail on the north side of the lobby.

Please check back at ltowerconstructioninfo.com for regular updates.

Surfacing and waterproofing work continues on the podium deck.

Surfacing and waterproofing work continues on the podium deck.

Friday, July 1 – Canada Day

NOTE: While there will be no work on site there may be residential move-ins. 

Saturday, July 2

  • Some general housekeeping work on site. 
  • Possible Move-ins 

Sunday, July 3

  • Possible Move-ins 
Support struts in the parking garage for the east tower mast climber

Support struts in the parking garage for the east tower mast climber

Monday, July 4

  • Cladding installation and exterior work.
  • Drywall and finishing work in unoccupied suites, lobby and amenity areas.  
  • Toro Aluminum doing repair working on-site. 

Tuesday, July 5

  • Cladding installation and exterior work.
  • Drywall and finishing work in unoccupied suites, lobby and amenity areas.  
  • Toro Aluminum doing repair working on-site.

Wednesday, July 6

  • Cladding installation and exterior work.
  • Drywall and finishing work in unoccupied suites, lobby and amenity areas.  
  • Toro Aluminum doing repair working on-site.
Completed third floor garage at Backstage

Completed third floor garage at Backstage

Thursday, July 7

  • Cladding installation and exterior work.
  • Drywall and finishing work in unoccupied suites, lobby and amenity areas.  
  • Toro Aluminum doing repair working on-site.

Friday, July 8

  • Cladding installation and exterior work.
  • Drywall and finishing work in unoccupied suites, lobby and amenity areas.  
  • Toro Aluminum doing repair working on-site.
East face of the Backstage podium

East face of the Backstage podium

L Tower update July 1

L Tower construction information 8 The Esplanade – L Tower July 1

Work on the L Tower’s east side is proceeding as windows are being installed where the former crane support struts connected to the building.

Work on the northwest plaza continues to proceed. Designed by Claude Cormier and Associates and featuring a major new public art installation by Harley Valentine, it will be a signature gateway to the neighbourhood when it opens later this year.

Ongoing clean up at street level will continue in preparation for sidewalk work over summer.  Check back here at ltowerconstructioninfo.com for regular updates. 

L Tower adding glazing where the tower crane struts formerly attached to the east side of the tower

L Tower adding glazing where the tower crane struts formerly attached to the east side of the tower

Work on the northwest plaza at the Sony Centre continues to proceedWork on the northwest plaza at the Sony Centre continues to proceed

Sidewalk area that will be improved over the summer months

Sidewalk area that will be improved over the summer months

Backstage Construction Update – June 25 – July 1, 2016

This is a construction update for Backstage Condominium, 1 The Esplanade, June 25 – July 1, 2016

Exterior work at the backstage takes another step forward as a tower hoist or mast climber is being built on the east side of the tower in preparation for the installation of porcelain panels on the fins.  Porcelain tile installation continues on the west side of the tower and is now up to approx. the 7th floor. Stucco work is underway and continues this week on the northeast side of the podium.

The outdoor amenity space on the podium deck is being waterproofed and its surface is being prepared for the installation of pavers and landscaping. 

Interior work this week sees the return of drywallers and related trades permitting work to resume in the unfinished amenity areas and the lower suites.

Residents have started parking on the first 3 levels that were opened up last week.

Please check back at ltowerconstructioninfo.com for regular updates.

Waterproofing work on the podium outdoor amenity space

Waterproofing work on the podium outdoor amenity space

Saturday, June 25

  • General housekeeping work on site. 
Porcelain tiles installed on the west tower fins at Backstage

Porcelain tiles installed on the west tower fins at Backstage

Monday, June 27

  • Cladding installation and exterior work.
  • Drywall and finishing work in unoccupied suites, lobby and amenity areas.  

Tuesday, June 28

  • Cladding installation and exterior work.
  • Drywall and finishing work in unoccupied suites, lobby and amenity areas.  

Wednesday, June 29

  • Cladding installation and exterior work.
  • Drywall and finishing work in unoccupied suites, lobby and amenity areas.  

Thursday, June 30

  • Cladding installation and exterior work.
  • Drywall and finishing work in unoccupied suites, lobby and amenity areas.  
Kitchen intallation resumes in an unoccupied suite at Backstage

Kitchen installation resumes in an unoccupied suite at Backstage

Friday, July 1st – site closed for CANADA DAY 

Tower hoist installed on the east tower at Backstage

Tower hoist installed on the east tower at Backstage

 

L Tower update June 18 – 28

L Tower construction information 8 The Esplanade – L Tower –  June 18 – 28

Work on the L tower is now focussed on completing installation the permanent maintenance platform at the top of the tower and installing glazing where the support struts for the crane connected to the east side of the tower. As well there will be ongoing clean up at street level in preparation for streetscaping work to begin later this summer.  Check back here at ltowerconstructioninfo.com for regular updates. 

Work contiunes to install the permanent maintence platform at the top of the L Tower

Work continues to install the permanent maintenance platform at the top of the L Tower

  •  Windows will be installed in the areas where the strut supports for the crane had been attached to the building. 
  • Sidewalk work will follow once all exterior tower work is completed.
  • The maintenance platform on the top floor will be completed in the coming weeks.
  • The NW plaza at the Sony Centre will continue to worked on and is set to open later this year. 
Surfacing underlay at the Sony Centre NW plaza

Surfacing underlay at the Sony Centre NW plaza

The final window areas on the east side of the tower that are waiting to be finished with glazing.

The final window areas on the east side of the tower that are waiting to be finished with glazing.

Backstage Construction Update – June 18 – 24, 2016

This is a construction update for Backstage Condominium, 1 The Esplanade, June 18 – 24, 2016

Progress is being made on the east face of the podium with the limestone cladding installation. Further along the east wall the stucco exterior has been started and is starting to take shape.

At the west end of the tower the porcelain tile is starting to work its way up the building (examples pictured below).

The drywallers are back to work and are proceeding to play catch up within certain areas of the interior with a particular area of focus being the lobby.

A mobile crane has arrived on site to start with the erection of the mast climber to facilitate the installation of the porcelain tile on the fins.

Parking on the first three levels will now be initiated to allow residents in Backstage to park their vehicles on the premises.

Please check back at ltowerconstructioninfo.com for regular updates.

Examples of Limestone and Porcelain exterior cladding.

Examples of Limestone and Porcelain exterior cladding.

Saturday, June 18

  • General housekeeping work on site. 
Porcelain tile being installed on the %22fins%22 at Backstage

Porcelain tile being installed on the fins at Backstage

Monday, June 20

  • Cladding installation and exterior work.
  • Drywall and finishing work in unoccupied suites, lobby and amenity areas.  

Tuesday, June 21

  • Cladding installation and exterior work.
  • Drywall and finishing work in unoccupied suites, lobby and amenity areas.  

Wednesday, June 22

  • Cladding installation and exterior work.
  • Drywall and finishing work in unoccupied suites, lobby and amenity areas.  

Thursday, June 23

  • Cladding installation and exterior work.
  • Drywall and finishing work in unoccupied suites, lobby and amenity areas.  

Friday, June 25

  • Cladding installation and exterior work.
  • Drywall and finishing work in unoccupied suites, lobby and amenity areas.  
Looking up Backstage from the podium to the top of the tower.

Looking up Backstage from the podium to the top of the tower.

 

 

L Tower update June 11 – 17

L Tower construction information 8 The Esplanade – L Tower –  June 11 – 17

Work on the L tower is now focussed on installing windows where the support struts for the crane connected to the tower and at street level; as well as cleaning up the street level in preparation for streetscaping work to begin.  Check back here at ltowerconstructioninfo.com for regular updates. 

L Tower monochrome

L Tower monochrome

  • Windows will be installed in the areas where the strut supports for the crane had been attached to the building. 
  • Sidewalk work will follow once all exterior tower work is completed.
  • The maintenance platform on the top floor will be completed in the coming weeks.
  • The NW plaza at the Sony Centre will continue to worked on and is set to open later this year. 
St. Lawrence Market Neighbourhood seen from the L Tower

St. Lawrence Market Neighbourhood seen from the L Tower

Backstage Construction Update – June 11 – 17, 2016

This is a construction update for Backstage Condominium, 1 The Esplanade, June 11 – 17, 2016

Interior work at Backstage remains slowed down by the ongoing drywall strike.  On the positive side other trades not affected by the strike are caught up with their work.

On the exterior the front elevation of the podium caulking has been in-progress this week at the limestone joints. As well, the porcelain tile has started and can be seen on the west elevation beside the lobby entrance off Yonge Street. Stucco work has begun on the exterior wall between Backstage and Green P.

Where possible, inside the building, construction crews are working on suites which were previously not sold and hoist suites on the east side of the tower, installing the kitchens and flooring where the main drywall work has already been completed.

Please check back at ltowerconstructioninfo.com for regular updates.

Looking east from Backstage's podium deck

Looking east from Backstage’s podium deck beside the future swimming pool.

Saturday, June 11

  • General housekeeping work on site. 
Amenity area awaiting finishing work and additional drywall (when the labour action is over).

Amenity area awaiting finishing and additional drywall (when the labour action is over).

Monday, June 13

  • Cladding installation and exterior work.
  • Some finishing work on unoccupied suites with completed drywall.

Tuesday, June 14

  • Cladding installation and exterior work.
  • Some finishing work on unoccupied suites with completed drywall.

Wednesday, June 15

  • Cladding installation and exterior work.
  • Some finishing work on unoccupied suites with completed drywall.

Thursday, June 16

  • Cladding installation and exterior work.
  • Some finishing work on unoccupied suites with completed drywall.

Friday, June 17

  • Cladding installation and exterior work.
  • Some finishing work on unoccupied suites with completed drywall.
Looking west to the Backstage tower and the L Tower from the podium deck.

Looking west from the podium to the Backstage tower “hoist suites” in the centre of the tower where finishing work is occurring in unoccupied suites. 

Backstage Construction Update – June 4 – 10, 2016

This is a construction update for Backstage Condominium, 1 The Esplanade, June 4 – 10, 2016

Work at Backstage continues to progress at a steady pace. On the north face of the podium construction workers are caulking the stone joints. On the west face of the tower work is ongoing to prepare for the installation of the porcelain tile that will clad the “fins” that rise the full height of the building. 

The ongoing labour disruption in key trades, such as drywallers, continues to slow finishing work for suites that were not completed prior to strike action commencing. 

There is ongoing preparation and testing for the parking levels. Crews have worked with City of Toronto staff to complete some of the key tests. Formal inspections for the parking levels are expected to be completed by mid-June. 

 

Please check back at ltowerconstructioninfo.com for regular updates.

View south from the future indoor amenity psace on the 5th floor of Backstage

View south from the future indoor amenity psace on the 5th floor of Backstage

Saturday, June 4

  • Possible move-ins.
  • General housekeeping work on site. 

Monday, June 6

  • Cladding installation and exterior work.
  • Interior work on the parking levels. 

Tuesday, May 7

  • Cladding installation and exterior work.
  • Interior work on the parking levels. 
The podium deck outdoor amenity space at Backstage looking east

The podium deck outdoor amenity space at Backstage looking east

Wednesday, June 8

  • Cladding installation and exterior work.
  • Interior work on the parking levels

Thursday, June 9

  • Cladding installation and exterior work.
  • Interior work on the parking levels

Friday, June 10

  • Cladding installation and exterior work.
  • Interior work on the parking levels
Looking up at the east face of Backstage

Looking up at the east face of Backstage

L Tower update June 1 – 10

L Tower construction information 8 The Esplanade – L Tower –  June 1 – 10

Since the L tower crane was successfully removed on May 18th work continues to prepare for the in the final phases of remaining exterior work, including window glazing where the support struts for the crane connected to the tower and at street level. Check back here at ltowerconstructioninfo.com for regular updates. 

L Tower southwest corner looking west to the Financial District

L Tower southwest corner looking west to the Financial District

L Tower May 27, 2016

L Tower May 27, 2016

  • Windows will be installed in the areas where the strut supports for the crane had been attached to the building. 
  • Sidewalk work will follow once all exterior tower work is completed.
  • The maintenance platform on the top floor will be completed in the coming weeks.
  • The NW plaza at the Sony Centre will continue to worked on and is set to open later this year. 
L Tower sans crane

L Tower sans crane

L Tower at grade, where future sidewalk work will occur now that the crane has been removed, May 27 2016

L Tower at grade, where future sidewalk work will occur now that the crane has been removed, May 27 2016

 