Backstage Construction Update May 28 – June 3, 2016
May 27, 2016 Leave a comment
This is a construction update for Backstage Condominium, 1 The Esplanade May 28 – June 3, 2016
Work continues to progress on the exterior cladding at Backstage. Starting Monday, the installation of porcelain tile on the “fins” on the west side of the tower will commence, depending on weather conditions.
The installation of limestone cladding continues on the north face of the podium, and will soon begin on the west side of the building.
Backstage has been approved for occupancy for “Hoist Suites” on the east side of the tower, from the 9th to 19th floor. Unfortunately there are areas which are still on hold due to the ongoing labour action by key unions, slowing progress on finishing interiors, such as some of the podium suites and indoor amenity areas. The outdoor amenity area on the podium deck will see work commence in the coming weeks, we will have updates on this in the near future.
Please check back at ltowerconstructioninfo.com for regular updates.
Saturday, May 28
- Possible move-ins.
- General housekeeping work on site.
Sunday, May 29
- Possible move-ins.
Monday, May 30
- Cladding installation and exterior work.
Tuesday, May 31
- Cladding installation and exterior work.
Wednesday, June 1
- Cladding installation and exterior work.
Thursday, June 2
- Cladding installation and exterior work.
Friday, June 3
- Cladding installation and exterior work.