Backstage Construction Update May 21 – 27, 2016
May 20, 2016 Leave a comment
This is a construction update for Backstage Condominium, 1 The Esplanade May 21 – 27, 2016
Work at Backstage in the past week was slwed from th contnuing labour action by the drywall and tiling unions. The road closure for the removal of the L Tower’s crane also had an impact. Work continues to progress on the north face of the podium and the west face of the tower.
Traffic topping (waterproofing) on the ground floor parking garage and the main drive entrance concrete was completed. The lines have been painted for the parking on Levels 1 and 2.
Inside the building some wallpaper is continuing in the corridors and with more suites being prepared for occupancy inspections next week.
Please check back at ltowerconstructioninfo.com for regular updates.
Saturday, May 21
- Possible move-ins.
- General housekeeping work on site.
Sunday, May 22
- Possible move-ins.
Monday, May 23 – Victoria Day Holiday
- SITE CLOSED.
Tuesday, May 24
- Cladding installation and exterior work.
- Interior suite work and finishing.
Wednesday, May 25
- Cladding installation and exterior work.
- Interior suite work and finishing.
Thursday, May 26
- Cladding installation and exterior work.
- Interior suite work and finishing.
Friday, May 27
- Cladding installation and exterior work.
- Interior suite work and finishing.