Backstage Construction Update May 14 – 20, 2016
May 13, 2016 Leave a comment
This is a construction update for Backstage Condominium, 1 The Esplanade May 14 – 20, 2016
On the west side of the tower, workers are still preparing the substrate (metal supports) for the porcelain tile which will cover the “tower fins;” a sample of the porcelain is shown below. The installation of the porcelain tile should begin, depending on weather, within a couple of weeks.
Limestone cladding work is progressing well on the north elevation of the podium.
The ground floor traffic topping (waterproofing) is complete. Painting lines on the ground floor parking garage will begin once the topping is fully cured. This work should get underway this coming week.
Please check back at ltowerconstructioninfo.com for regular updates.
Saturday, May 14
- Move-ins continue.
- General housekeeping work on site.
Sunday, May 15
- Possible move-ins.
Monday, May 16
- Vehicle Road Closure on The Esplanade to permit the removal of the final sections of the L Tower crane.
- Claddinginstallation and exterior work.
Tuesday, May 17
- Vehicle Road Closure on The Esplanade to permit the removal of the final sections of the L Tower crane.
- Cladding installation and exterior work.
Wednesday, May 18
- Vehicle Road Closure on The Esplanade to permit the removal of the final sections of the L Tower crane.
- Painting ground floor garage level.
- Cladding installation and exterior work.
Thursday, May 19
- Move-ins continue.
- Painting ground floor garage level.
- Cladding installation and exterior work.
Friday, May 20
- Move-ins continue.
- Painting ground floor garage level.
- Cladding installation and exterior work.