Backstage Construction Update May 7 – 13, 2016
May 6, 2016 Leave a comment
This is a construction update for Backstage Condominium, 1 The Esplanade May 7 – 13, 2016
Construction crews are continuing with the stone on the front face of the podium and the tower stone brackets on the west side of the tower. On the interior waterproofing the grey surface for the parking level is ongoing and will be complete in a couple of weeks. Occupancy has now been approved for 35th and 36th floors.
Work is proceeding more slowly in the amenity areas. Much of the interior work in remaining on the lower floor suites and amenity areas has been delayed due to a strike by the drywall and tiling unions.
Please check back at ltowerconstructioninfo.com for regular updates.
Saturday, May 7
- Move-ins continue.
- General housekeeping work on site.
Sunday, May 8
- Possible move-ins.
Monday, May 9
- Move-ins continue.
- Waterproofing ground floor parking level.
- Claddinginstallation and exterior work.
Tuesday, May 10
- Move-ins continue.
- Waterproofing ground floor parking level.
- Cladding installation and exterior work.
Wednesday, May 11
- Move-ins continue.
- Waterproofing ground floor parking level.
- Cladding installation and exterior work.
Thursday, May 12
- Move-ins continue.
- Waterproofing ground floor parking level.
- Cladding installation and exterior work.
Friday, May 13
- Move-ins continue.
- Waterproofing ground floor parking level.
- Cladding installation and exterior work.