Backstage Construction Update April 9 – 15, 2016
April 8, 2016 Leave a comment
This is a construction update for Backstage Condominium, 1 The Esplanade April 9 – 15, 2016
In the past week construction efforts have faced a few slowdowns on the exterior due to the unseasonable weather. Even with these conditions, the Limestone is continuing to be installed up the North face of the building. The porcelain tile cladding of the ‘fins’ on the West side of the tower is also continuing. Railing glass has been completed at the Southwest corner of the tower and these railings have been inspected, and passed.
On the interior, suites have been completed up to the 34th floor. The Kitchens are in on 35th and 36th with flooring work in-progress. Building occupancy inspections for the 31st to 34th floors are currently in-progress with the various consultants and the Building Inspector. These should be completed this coming week. Move-ins will follow for the units that have been completed and successfully inspected.
Please check back at ltowerconstructioninfo.com for regular updates.
Saturday, April 9
- Move-ins continue.
- Interior suite work: drywall and final finishing.
- General housekeeping work on site.
Sunday, April 10
- Possible move-ins.
Monday, April 11
- Move-ins continue.
- Interior suite work: drywall and final finishing.
- Tower and podium cladding installation and glazing.
Tuesday, April 12
- Move-ins continue.
- Interior suite work: drywall and final finishing.
- Tower and podium cladding installation and glazing.
Wednesday, April 13
- Move-ins continue.
- Interior suite work: drywall and final finishing.
- Tower and podium cladding installation and glazing.
Thursday, April 14
- Move-ins continue.
- Interior suite work: drywall and final finishing.
- Tower and podium cladding installation and glazing.
Friday, April 15
- Move-ins continue.
- Interior suite work: drywall and final finishing.
- Tower and podium cladding installation and glazing.