Backstage Construction Update April 9 – 15, 2016

This is a construction update for Backstage Condominium, 1 The Esplanade April 9 – 15, 2016

In the past week construction efforts have faced a few slowdowns on the exterior due to the unseasonable weather. Even with these conditions, the Limestone is continuing to be installed up the North face of the building. The porcelain tile cladding of the ‘fins’ on the West side of the tower is also continuing.  Railing glass has been completed at the Southwest corner of the tower and these railings have been inspected, and passed. 

On the interior, suites have been completed up to the 34th floor.  The Kitchens are in on 35th and 36th with flooring work in-progress.  Building occupancy inspections for the 31st to 34th floors are currently in-progress with the various consultants and the Building Inspector. These should be completed this coming week. Move-ins will follow for the units that have been completed and successfully inspected. 

Please check back at ltowerconstructioninfo.com for regular updates.

West face of Backstage tower section

West face of Backstage tower section

Saturday, April 9

  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • General housekeeping work on site. 

Sunday, April 10

  • Possible move-ins.
A finished hallway on the 8th floor at Backstage

A finished hallway on the 8th floor at Backstage

Monday, April 11

  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Tower and podium cladding installation and glazing.

Tuesday, April 12

  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Tower and podium cladding installation and glazing.
Installing limestone cladding on the podium in an the chilly April weather

Installing limestone cladding on the podium in an the chilly April weather.

Wednesday, April 13

  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Tower and podium cladding installation and glazing.

Thursday, April 14

  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Tower and podium cladding installation and glazing.

Friday, April 15

  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Tower and podium cladding installation and glazing.
Podium unit in progress at Backstage

Podium unit in progress at Backstage

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: