Backstage Construction Update April 2 – 8, 2016
April 1, 2016 Leave a comment
This is a construction update for Backstage Condominium, 1 The Esplanade April 2 – 8, 2016
With the improving weather the installation of limestone cladding has been progressing on the north face of the building. Cladded the west elevation ‘fins’ is underway and continues through the week. On the southwest corner by the railway corridor, railings with tempered glass are being installed on the balconies. In the northeast corner of the building Toro Aluminum is installing the balance of the balcony ‘wing’ windows.
Kitchens and appliances have been installed from the 8th floor to the 34th floor along with the hardwood flooring. Corridors and elevator lobbies have been wallpapered and flooring installed up to 31st floor. Residents have moved in (or are moving in) up to the 30th floor. There will inspections in the coming week in preparation for the next set of move-ins to floors 31 – 34.
Please check back at ltowerconstructioninfo.com for regular updates.
Saturday, April 2
- Move-ins continue.
- Interior suite work: drywall and final finishing.
- General housekeeping work on site.
Sunday, April 3
- Possible move-ins.
Monday, April 4
- Move-ins continue.
- Interior suite work: drywall and final finishing.
- Tower and podium cladding installation and glazing.
Tuesday, April 5
- Move-ins continue.
- Interior suite work: drywall and final finishing.
- Tower and podium cladding installation and glazing.
Wednesday, April 6
- Move-ins continue.
- Interior suite work: drywall and final finishing.
- Tower and podium cladding installation and glazing.
Thursday, April 7
- Move-ins continue.
- Interior suite work: drywall and final finishing.
- Tower and podium cladding installation and glazing.
Friday, April 8
- Move-ins continue.
- Interior suite work: drywall and final finishing.
- Tower and podium cladding installation and glazing.