Backstage Construction Update – March 28 – April 1, 2016
March 28, 2016 Leave a comment
This is a construction update for Backstage Condominium, 1 The Esplanade March 28 – April 1, 2016
Occupancy at Backstage has reached the 30th floor. Last week’s bad weather slowed progress on the exterior work. Interior suite finishing continues on the top tower floors. Work on the podium exterior, tower and podium deck are resuming this week. Work will also be occurring on the 3rd and 4th floor parking levels.
Moving trucks may have some limited impact on eastbound traffic flows as new residents move in but pedestrian access to and from Yonge Street will be unaffected.
Please check back at ltowerconstructioninfo.com for regular updates.
Monday, March 28
- Move-ins continue.
- Interior suite work: drywall and final finishing.
- Podium cladding installation and glazing installation on the tower..
Tuesday, March 29
- Move-ins continue.
- Interior suite work: drywall and final finishing.
- Podium cladding installation and glazing installation on the tower.
- Finishing work on the 3rd and 4th floor parking levels.
Wednesday, March 30
- Move-ins continue.
- Interior suite work: drywall and final finishing.
- Podium cladding installation and glazing installation on the tower.
- Finishing work on the 3rd and 4th floor parking levels.
Thursday, March 31
- Move-ins continue.
- Interior suite work: drywall and final finishing.
- Podium cladding installation and glazing installation on the tower.
- Finishing work on the 3rd and 4th floor parking levels.
Friday, April 1
- Move-ins continue.
- Interior suite work: drywall and final finishing.
- Podium cladding installation and glazing installation on the tower..