Backstage Construction Update – March 19 – 25, 2016
March 18, 2016 Leave a comment
This is the construction schedule for Backstage Condominium, 1 The Esplanade March 19 – 25, 2016
Move-ins continue at Backstage through the weekend and the coming week. Interior suite finishing continues on the upper level floors. Work on the podium deck will moves into higher gear over the next few weeks with the improving weather.
Moving trucks and occasional deliveries by truck will occur as needed. These will have some limited impact on eastbound traffic flows but pedestrian access to and from Yonge Street will be unaffected.
Please check back at ltowerconstructioninfo.com for updates in the coming week.
Saturday, March 19
- Move-ins continue.
- Interior suite work.
- Housekeeping work on site.
Sunday, March 20
- Move-ins continue.
Monday, March 21
- Move-ins continue.
- Interior suite work: drywall and final finishing.
- Podium cladding installation and window installation on the southeast elevation.
Tuesday, March 22
- Move-ins continue.
- Interior suite work: drywall and final finishing.
- Podium cladding installation and window installation on the southeast elevation.
Wednesday, March 23
- Move-ins continue.
- Interior suite work: drywall and final finishing.
- Podium cladding installation and window installation on the southeast elevation.
Thursday, March 24
- Move-ins continue.
- Interior suite work: drywall and final finishing.
- Podium cladding installation and window installation on the southeast elevation.
Friday, March 25
- Move-ins continue.
- Interior suite work: drywall and final finishing.
- Podium cladding installation and window installation on the southeast elevation.