Backstage Construction Update – March 12 – 18, 2016
March 11, 2016 Leave a comment
This is the construction schedule for Backstage Condominium, 1 The Esplanade March 12 – 18, 2016
Tower suites up to the 26th floor are ready for the occupancy as move-ins to Backstage continue through the weekend and the coming weekdays. With the spring-like conditions work on balcony glazing and the podium facade will pick up. Interior suite finishing continues from the 27th through 36th floors. Work on the podium deck will move into higher gear over the next few weeks with the improving weather.
Occasional deliveries will occur as needed with minimal impact on the street or traffic flows.
Please check back at ltowerconstructioninfo.com for updates in the coming week.
Saturday, March 12
- Move-ins continue.
- Interior suite work.
- Housekeeping work on site.
Sunday, March 13
- Move-ins continue.
Monday, March 14
- Move-ins continue.
- Interior suite work: drywall and final finishing.
- Podium cladding installation and window installation on the southeast elevation.
Tuesday, March 15
- Kitchen cabinet delivery.
- Move-ins continue.
- Interior suite work: drywall and final finishing.
- Podium cladding installation and window installation on the southeast elevation.
- Third and fourth floor garage floors painted in preparation for use by new residents.
Wednesday, March 16
- Move-ins continue.
- Interior suite work: drywall and final finishing.
- Podium cladding installation and window installation on the southeast elevation.
- Third and fourth floor garage floors painted in preparation for use by new residents.
Thursday, March 17
- Move-ins continue.
- Interior suite work: drywall and final finishing.
- Podium cladding installation and window installation on the southeast elevation.
Friday, March 18
- Move-ins continue.
- Interior suite work: drywall and final finishing.
- Podium cladding installation and window installation on the southeast elevation.