L Tower February – March 2016

L Tower construction information 8 The Esplanade – L Tower  February – March 2016

Updated March 30, 2016

Overall:

Move-ins continue at L Tower. Suite and interior work continues on the few remaining unfinished units.

The tower crane remains in-place as the final work to install the rooftop maintenance unit has not yet been completed. We expect this work to be underway in and completed in April. When we have dates for the completion of this work and the lowering of the tower crane we will post them here. Please check back for updates. 

St. Lawrence Market Neighbourhood as seen from the L Tower

St. Lawrence Market Neighbourhood as seen from the L Tower

L Tower: the tower crane is scheduled to be taken down in March.

L Tower: the tower crane is scheduled to be taken down in March.

Tower Crane:

The exterior tower crane will remains up. The new derrick and related equipment that will enable the installation of the permanent maintenance platform for the building was not available when originally expected. Therefore the installation of the derrick which requires the tower crane to lift into place will not occur until April. Similarly we now expect the the tower crane to be lowered in Apirl.  We will have updates on the timing of this as they become available. 

Tower crane at L Tower

Tower crane at L Tower

Sony Centre NW Plaza

Work on the northwest plaza of the Sony Centre, immediately north of the L Tower was scheduled to commence this month. but inconsistent weather has interfered with timelines. We expect work will begin sometime in April. Once again we’ll post updates here once they become available. 

Sony Centre Plaza design by Claude Cormier et associés: http://www.claudecormier.com/en/projet/sony-center-for-the-performing-arts/

Sony Centre Plaza design by Claude Cormier + Associés: http://www.claudecormier.com/en/projet/sony-center-for-the-performing-arts/

NOTE for L Tower Residents

We get enquires from L Tower residents about the progress of internal work in the building. While we are happy to direct these enquiries to the appropriate people, please note that the purpose of this site is to provide construction information to external neighbourhood stakeholders, particularly in the immediate St. Lawrence Market neighbourhood.

L Tower residents tunnel access to the parking garage

L Tower residents tunnel access to the parking garage

 

Backstage Construction Update – March 28 – April 1, 2016

This is a construction update for Backstage Condominium, 1 The Esplanade March 28 – April 1, 2016

Occupancy at Backstage has reached the 30th floor. Last week’s bad weather slowed progress on the exterior work. Interior suite finishing continues on the top tower floors. Work on the podium exterior, tower and podium deck are resuming this week. Work will also be occurring on the 3rd and 4th floor parking levels. 

Moving trucks may have some limited impact on eastbound traffic flows as new residents  move in but pedestrian access to and from Yonge Street will be unaffected. 

Please check back at ltowerconstructioninfo.com for regular updates.

Backstage podium facade work

Backstage podium facade work

Monday, March 28

  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Podium cladding installation and glazing installation on the tower..

Tuesday, March 29

  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Podium cladding installation and glazing installation on the tower.
  • Finishing work on the 3rd and 4th floor parking levels. 

Wednesday, March 30

  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Podium cladding installation and glazing installation on the tower.
  • Finishing work on the 3rd and 4th floor parking levels. 

Thursday, March 31

  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Podium cladding installation and glazing installation on the tower.
  • Finishing work on the 3rd and 4th floor parking levels.

Friday, April 1

  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Podium cladding installation and glazing installation on the tower..
Carpeted hallway at Backstage

Carpeted hallway at Backstage

Backstage Construction Easter Weekend Update – March 25 – 27, 2016

This is the Easter Weekend construction update for Backstage Condominium, 1 The Esplanade March 25 – 27, 2016

Move-ins continue at Backstage through the holiday weekend. Thursday’s ice storm impacted exterior work. However, interior suite finishing continues on the upper level floors continues on Saturday. Work on the podium exterior, tower and podium deck will resume next week. 

Moving trucks may have some limited impact on eastbound traffic flows but pedestrian access to and from Yonge Street will be unaffected. 

Please check back at ltowerconstructioninfo.com on Monday March 28 for next week’s update.

Friday, March 25 – Good Friday – site closed. 

  • Move-ins may occur.

Saturday, March 26

  • Move-ins continue.
  • Interior suite work.
  • Housekeeping work on site.

Sunday, March 27 – Easter Sunday

  • Move-ins may occur.
Bathroom 1:2 way to finished.

Bathroom 1/2 way to finished.

 

Backstage Construction Update – March 19 – 25, 2016

This is the construction schedule for Backstage Condominium, 1 The Esplanade March 19 – 25, 2016

Move-ins continue at Backstage through the weekend and the coming week.  Interior suite finishing continues on the upper level floors. Work on the podium deck will moves into higher gear over the next few weeks with the improving weather. 

Moving trucks and occasional deliveries by truck will occur as needed. These will have some limited impact on eastbound traffic flows but pedestrian access to and from Yonge Street will be unaffected. 

Please check back at ltowerconstructioninfo.com for updates in the coming week.

Saturday, March 19

  • Move-ins continue.
  • Interior suite work.
  • Housekeeping work on site.

Sunday, March 20

  • Move-ins continue.
L Tower and Backstage March 18, 2016

L Tower and Backstage March 18, 2016

Monday, March 21

  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Podium cladding installation and window installation on the southeast elevation.

Tuesday, March 22

  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Podium cladding installation and window installation on the southeast elevation.

Wednesday, March 23

  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Podium cladding installation and window installation on the southeast elevation.

Thursday, March 24

  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Podium cladding installation and window installation on the southeast elevation.

Friday, March 25

  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Podium cladding installation and window installation on the southeast elevation.
Backstage 36th floor suite looking west.

Backstage 36th floor suite looking west.

Backstage Construction Update – March 12 – 18, 2016

This is the construction schedule for Backstage Condominium, 1 The Esplanade March 12 – 18, 2016

Tower suites up to the 26th floor are ready for the occupancy as move-ins to Backstage continue through the weekend and the coming weekdays. With the spring-like conditions work on balcony glazing and the podium facade will pick up.  Interior suite finishing continues from the 27th through 36th floors. Work on the podium deck will move into higher gear over the next few weeks with the improving weather. 

Occasional deliveries will occur as needed with minimal impact on the street or traffic flows. 
Please check back at ltowerconstructioninfo.com for updates in the coming week.

Southeast view from Backstage 36th floor

Southeast view from Backstage 36th floor

Saturday, March 12

  • Move-ins continue.
  • Interior suite work.
  • Housekeeping work on site.

Sunday, March 13

  • Move-ins continue.
28th floor suite looking east at Backstage

28th floor suite looking east at Backstage

Monday, March 14

  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Podium cladding installation and window installation on the southeast elevation.

Tuesday, March 15

  • Kitchen cabinet delivery. 
  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Podium cladding installation and window installation on the southeast elevation.
  • Third and fourth floor garage floors painted in preparation for use by new residents. 

Wednesday, March 16

  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Podium cladding installation and window installation on the southeast elevation.
  • Third and fourth floor garage floors painted in preparation for use by new residents. 

Thursday, March 17

  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Podium cladding installation and window installation on the southeast elevation.

Friday, March 18

  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Podium cladding installation and window installation on the southeast elevation.
Backstage tower hallways almost finished.

Backstage tower hallways almost finished.

Backstage Construction Update – March 5 – 11, 2016

This is the construction schedule for Backstage Condominium, 1 The Esplanade March 5 – 11, 2016

Suites up to the 25th floor are ready for the occupancy as move-ins to Backstage continue through the weekend and the coming week. Exterior glazing on tower is ongoing as is facade work on the podium but both are weather dependent. Interior suite finishing continues ftom the 26th through 36th floors. 

Occasional deliveries will occur as needed with minimal impact on the street or traffic flows. 
Please check back at ltowerconstructioninfo.com for updates in the coming week.
View west from Backstage

View west from Backstage

Saturday, March 5

  • Move-ins continue.
  • Interior suite work.
  • Housekeeping work on site.

Sunday, March 6

  • Possible move-ins.

Monday, March 7

  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Podium cladding installation and window installation on the southeast elevation.

Tuesday, March 8

  • Kitchen cabinet delivery. 
  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Podium cladding installation and window installation on the southeast elevation.
  • Third and fourth floor garage floors painted in preparation for use by new residents. 

Wednesday, March 9

  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Podium cladding installation and window installation on the southeast elevation.
  • Third and fourth floor garage floors painted in preparation for use by new residents. 

Thursday, March 10

  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Podium cladding installation and window installation on the southeast elevation.

Friday, March 11

  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Podium cladding installation and window installation on the southeast elevation.

 

  • Backstage unfinished suite

    Backstage unfinished suite