Backstage Construction Update – February 13 – 19, 2016

This is the construction schedule for 1 The Esplanade, Backstage condominium – for February 13 – 19, 2016

Weather permitting, exterior work continues on the podium and the tower with cladding and glazing installation. Occasional deliveries will occur as needed with minimal impact on the street or traffic flows. Work continues on the interior of the building readying suites for occupancy. Move-ins to Backstage are underway
Please check back at
ltowerconstructioninfo.com for updates.

View NW from the penthouse at backstage

View NW from the penthouse at backstage

Please click on the link to download a printable PDF Summary Construction Schedule for February 13 -19: Backstage Construction Summary-Feb 13-19-2016

Saturday, February 13

  • Interior suite work.
  • Housekeeping work on site.

Monday, February 15 – Family Day Holiday

Backstage suite with balcony and interior work remaining

Backstage suite with balcony and interior work remaining

Tuesday, February 16 

  • Kitchen cabinet delivery. 
  • Interior suite work: drywall and finishing.
  • Weather conditions permitting: Work on the tower and podium exteriors continues.

Wednesday, February 17 

  • Interior suite work: drywall and finishing.
  • Weather conditions permitting: Work on the tower and podium exteriors continues. 

Thursday, February 18

  • Interior suite work: drywall and finishing.
  • Weather conditions permitting: Work on the tower and podium exteriors continues.

Friday, February 19

  • Interior suite work: drywall and finishing.
  • Weather conditions permitting: Work on the tower and podium exteriors continues
Unfinished SE penthouse suite

Unfinished SE penthouse suite

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: