Backstage Construction Update – February 6 – 12, 2016
February 5, 2016 Leave a comment
This is the construction schedule for 1 The Esplanade, Backstage condominium – for February 6 – 12, 2016
Exterior work is focussed on the podium and the tower as cladding and glazing are being installed. Access to the building from Yonge Street will open soon, with the removal of material from the site and the addition of paved walkways. Access to the parking garage lobby will be opened from The Esplanade. Occasional deliveries occur as needed with minimal impact on the street or traffic flows. Work continues on the interior of the building readying suites for occupancy; in particular penthouse suites are still being finished prior to the installation of kitchens and appliances. The first move-ins to Backstage are expected this month.
Please check back at ltowerconstructioninfo.com for updates.

Backstage future retail facade at The Esplanade and entrance to parking levels where scaffolding is shown to the right. The scaffolding will be removed and a paved walkway will be added.
Please click on the link to download a printable PDF Summary Construction Schedule for February 6 -12: Backstage Construction Summary-Feb 6-12-2016

Looking west from the 36th floor at Backstage as interior suite finishing continues on the penthouse level.
Saturday, February 6
- Interior suite work.
- Housekeeping work on site.
Monday, February 8
- Interior suite work: drywall and finishing.
- Work on the tower and podium exteriors continue.
- Site clean-up at grade.
Tuesday, February 9
- Kitchen cabinet delivery.
- Interior suite work: drywall and finishing.
- Work on the tower and podium exteriors continue.
- External generator adjacent Yonge and The Esplanade is scheduled to be removed.
External generator at Backstage scheduled to be removed on Tuesday February 9
Wednesday, February 10
- Interior suite work: drywall and finishing.
- Work on the tower and podium exteriors continue.
- Site clean-up at grade.
Thursday, February 11
- Interior suite work: drywall and finishing.
- Work on the tower and podium exteriors continue.
- Site clean-up at grade.
Friday, February 12
- Interior suite work: drywall and finishing.
- Work on the tower and podium exteriors continue.
- Site clean-up at grade.