Backstage Construction Update – February 27 – March 4, 2016

This is the construction schedule for 1 The Esplanade, Backstage condominium – for February 27 – March 4, 2016

Suites up to the 19th floor are ready for the occupancy as move-ins to Backstage continue through the weekend and the coming week. Exterior work, to install the podium cladding and balcony glazing, that was delayed by inclement weather continues. Occasional deliveries will occur as needed with minimal impact on the street or traffic flows. The 3rd and 4th floor parking levels will have their lines painted prior to opening to new residents. Work also continues on the interior of the building the remaining unfinished suites for occupancy. 
Please check back at ltowerconstructioninfo.com for updates.

Penthouse unit with some remainig finishing work, looking east southeast

Penthouse unit with some remaining finishing work, looking east southeast

Please click on the link to download a printable PDF Summary Construction Schedule for February 27 – March 4: Backstage Construction Summary-Feb 27-Mar 4-2016

Saturday, February 27

  • Move-ins continue.
  • Interior suite work.
  • Housekeeping work on site.

Sunday, February 28

  • Possible move-ins.
Suites ready, hallways done, just a few more touches to do on this floor at Backstage

Suites ready, hallways done, just a few more touches to do on this floor at Backstage

Monday, February 22 

  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Podium cladding installation and window installation on the southeast elevation.

Tuesday, March 1

  • Kitchen cabinet delivery. 
  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Podium cladding installation and window installation on the southeast elevation.
  • Third and fourth floor garage floors painted in preparation for use by new residents. 

Wednesday, March 2

  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Podium cladding installation and window installation on the southeast elevation.
  • Third and fourth floor garage floors painted in preparation for use by new residents. 

Thursday, March 3

  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Podium cladding installation and window installation on the southeast elevation.

Friday, March 4

  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Podium cladding installation and window installation on the southeast elevation.
Newly installed garage door at Backstage

Newly installed garage door at Backstage

Backstage Construction Update – February 20 – 26, 2016

This is the construction schedule for 1 The Esplanade, Backstage condominium – for February 20 – 26, 2016

Move-ins to Backstage are underway and continue through the weekend and coming week. Exterior work continues on the podium’s cladding  and window installation on the southeast elevation. Occasional deliveries will occur as needed with minimal impact on the street or traffic flows. Work continues on the interior of the building readying the remaining unfinished suites for occupancy. 
Please check back at ltowerconstructioninfo.com for updates.

Looking East South East from the 36th floor of Backstage

Looking East Southeast from the 36th floor of Backstage

Please click on the link to download a printable PDF Summary Construction Schedule for February 20 – 26: Backstage Construction Summary-Feb 20-26-2016

Saturday, February 20

  • Move-ins continue.
  • Interior suite work.
  • Housekeeping work on site.

Sunday, February 21

  • Possible move-ins.

Monday, February 22 

  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Podium cladding installation and window installation on the southeast elevation.
Looking west from an unfinished suite at Backstage

Looking west from a Backstage penthouse suite in the process of being finished.

Tuesday, February 23 

  • Kitchen cabinet delivery. 
  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Podium cladding installation and window installation on the southeast elevation.

Wednesday, February 24

  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Podium cladding installation and window installation on the southeast elevation.

Thursday, February 25

  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Podium cladding installation and window installation on the southeast elevation.

Friday, February 26

  • Move-ins continue.
  • Interior suite work: drywall and final finishing.
  • Podium cladding installation and window installation on the southeast elevation.
Backstage penthouse suite in final stages of finishing.

Backstage penthouse suite in final stages of finishing.

Backstage Construction Update – February 13 – 19, 2016

This is the construction schedule for 1 The Esplanade, Backstage condominium – for February 13 – 19, 2016

Weather permitting, exterior work continues on the podium and the tower with cladding and glazing installation. Occasional deliveries will occur as needed with minimal impact on the street or traffic flows. Work continues on the interior of the building readying suites for occupancy. Move-ins to Backstage are underway
Please check back at
ltowerconstructioninfo.com for updates.

View NW from the penthouse at backstage

View NW from the penthouse at backstage

Please click on the link to download a printable PDF Summary Construction Schedule for February 13 -19: Backstage Construction Summary-Feb 13-19-2016

Saturday, February 13

  • Interior suite work.
  • Housekeeping work on site.

Monday, February 15 – Family Day Holiday

Backstage suite with balcony and interior work remaining

Backstage suite with balcony and interior work remaining

Tuesday, February 16 

  • Kitchen cabinet delivery. 
  • Interior suite work: drywall and finishing.
  • Weather conditions permitting: Work on the tower and podium exteriors continues.

Wednesday, February 17 

  • Interior suite work: drywall and finishing.
  • Weather conditions permitting: Work on the tower and podium exteriors continues. 

Thursday, February 18

  • Interior suite work: drywall and finishing.
  • Weather conditions permitting: Work on the tower and podium exteriors continues.

Friday, February 19

  • Interior suite work: drywall and finishing.
  • Weather conditions permitting: Work on the tower and podium exteriors continues
Unfinished SE penthouse suite

Unfinished SE penthouse suite

Backstage Construction Update – February 6 – 12, 2016

This is the construction schedule for 1 The Esplanade, Backstage condominium – for February 6 – 12, 2016

Exterior work is focussed on the podium and the tower as cladding and glazing are being installed. Access to the building from Yonge Street will open soon, with the removal of material from the site and the addition of paved walkways. Access to the parking garage lobby will be opened from The Esplanade. Occasional deliveries occur as needed with minimal impact on the street or traffic flows. Work continues on the interior of the building readying suites for occupancy; in particular penthouse suites are still being finished prior to the installation of kitchens and appliances. The first move-ins to Backstage are expected this month.
Please check back at
ltowerconstructioninfo.com for updates.

Backstage future retail facade at The Esplanade and entrance to parking levels where scaffolding is shown to the right. The scaffolding will be reoved and a paved walkway will be added.

Backstage future retail facade at The Esplanade and entrance to parking levels where scaffolding is shown to the right. The scaffolding will be removed and a paved walkway will be added.

Please click on the link to download a printable PDF Summary Construction Schedule for February 6 -12: Backstage Construction Summary-Feb 6-12-2016
Looking west from the 36th floor at Backstage as interior suite finishing continues.

Looking west from the 36th floor at Backstage as interior suite finishing continues on the penthouse level.

Saturday, February 6

  • Interior suite work.
  • Housekeeping work on site.

Monday, February 8 

  • Interior suite work: drywall and finishing.
  • Work on the tower and podium exteriors continue. 
  • Site clean-up at grade.

Tuesday, February 9

  • Kitchen cabinet delivery. 
  • Interior suite work: drywall and finishing.
  • Work on the tower and podium exteriors continue. 
  • External generator adjacent Yonge and The Esplanade is scheduled to be removed.

External generator at Backstage scheduled to be removed on Tuesday Feb 9External generator at Backstage scheduled to be removed on Tuesday February 9

Wednesday, February 10

  • Interior suite work: drywall and finishing.
  • Work on the tower and podium exteriors continue. 
  • Site clean-up at grade.

Thursday, February 11

  • Interior suite work: drywall and finishing.
  • Work on the tower and podium exteriors continue.
  •  Site clean-up at grade.
Backstage entrance from Yonge Street to prepared for use this week.

Backstage entrance from Yonge Street to prepared for use this week.

Friday, February 12

  • Interior suite work: drywall and finishing.
  • Work on the tower and podium exteriors continue. 
  • Site clean-up at grade.
South view from 36th floor at Backstage as penthouse suite finishing continues

South view from 36th floor at Backstage as penthouse suite finishing continues