Backstage Construction Update – January 23 – 29, 2016
January 22, 2016 Leave a comment
This is the construction schedule for 1 The Esplanade, Backstage condominium – for January 23 – 29, 2016
Fire damage to the podium roof from Wednesday’s accidental fire is minimal and will be cleaned this coming up week. As we and the media reported, there were no injuries, no structural damage and the fore was quickly put out due to the fast action of the on-site construction crew and the quick and efficient response from Toronto Fires Services. Exterior work continues on the podium and tower this coming week. Interior suite finishing continues. The first move-ins to Backstage are expected in February. Please check back for updates.

East view of the Backstage podium deck showing minimal fire damage from Wednesday’s fire and looking west showing no damage.
Please click on the link to download a printable PDF Summary Construction Schedule for January 23 – 29, 2016: Backstage Construction Summary-Jan-23-29-2016
Saturday, January 23
- Interior suite work.
- Housekeeping work on site, including cleaning the podium deck.
- Clearing fencing and materials from the construction area at Yonge & The Esplanade.
Monday, January 25
- Interior suite work: drywall and finishing.
- Work on the tower and podium exteriors continue.
Tuesday, January 26
- Interior suite work: drywall and finishing.
- Work on the tower and podium exteriors continue.
Wednesday, January 27
- Interior suite work: drywall and finishing.
- Work on the tower and podium exteriors continue.
Thursday, January 28
- Interior suite work: drywall and finishing.
- Work on the tower and podium exteriors continue.
Friday, January 29
- Interior suite work: drywall and finishing.
- Work on the tower and podium exteriors continue.