Backstage Construction Update – January 9 – 15, 2016
January 8, 2016 Leave a comment
This is the construction schedule for 1 The Esplanade, Backstage condominium – for January 8 – 15, 2016
As we enter the New Year, work has been gearing up at Backstage. Exterior work is concentrated on finishing the podium cladding and the balcony glazing on the southwest corner of the tower. Some deliveries continue with minor impacts on The Esplanade. We’ll have more information on approximate timelines for some of the key exterior work in the later part of the month. Please check back for daily updates which we post when there are notable changes to the construction schedule.
Please click on the link to download a printable PDF Summary Construction Schedule for January 8 – 15, 2016: Backstage Construction Summary-Jan-8-15-2016
Saturday, January 9
- Interior suite work.
- Housekeeping work on site
Monday, January 11
- Interior suite work: drywall and finishing.
- Work on the tower and podium exterior continues.
Tuesday, January 12
- Kitchen Appliance Delivery from 9 am.
- Interior suite work: drywall and finishing.
- Work on the podium exterior continues.
Wednesday, January 13
- Interior suite work: drywall and finishing.
- Work on the tower and podium exterior continues.
Thursday, January 14
- Interior suite work: drywall and finishing.
- Work on the tower and podium exterior continues.
Friday, January 15
- Interior suite work: drywall and finishing.
- Work on the tower and podium exterior continues.