Backstage Construction Update – January 30 – February 5, 2016
January 29, 2016 Leave a comment
This is the construction schedule for 1 The Esplanade, Backstage condominium – for January 30 – February 5, 2016
Work continues on the interior of the building readying suites for occupancy. Exterior work is focussed on the podium cladding and the tower, where windows and balcony glazing are being installed. Occasional deliveries may occur as needed with minimal impact on the street or traffic flows. The first move-ins to Backstage are expected in February and may start as soon as this coming week. Please check back at ltowerconstructioninfo.com for updates.
Please click on the link to download a printable PDF Summary Construction Schedule for January 30 – February 5: Backstage Construction Summary-Jan-30-Feb 5-2016
Saturday, January 30
- Interior suite work.
- Housekeeping work on site.
Monday, February 1
- Interior suite work: drywall and finishing.
- Work on the tower and podium exteriors continue.
Tuesday, February 2
- Interior suite work: drywall and finishing.
- Work on the tower and podium exteriors continue.
Wednesday, February 3
- Interior suite work: drywall and finishing.
- Work on the tower and podium exteriors continue.
Thursday, February 4
- Interior suite work: drywall and finishing.
- Work on the tower and podium exteriors continue.
Friday, February 5
- Interior suite work: drywall and finishing.
- Work on the tower and podium exteriors continue.