Backstage Construction Update – December 19 – January 1, 2016
December 18, 2015 Leave a comment
This is the construction schedule for 1 The Esplanade, Backstage condominium – for December 19, 2015 – January 1, 2016
Exterior work on the podium, suite finishing and on-site housekeeping are the focus of work at Backstage prior over the holidays with the site closed for Christmas, Boxing Day and New Year’s Day and limited activity in between the statutory holidays. This is our final post of 2015.
Best wishes for the holiday season and Happy New Year.
Please click on the link to download a printable PDF Summary Construction Schedule for Dec 19, 2015 – January 1, 2016: Backstage Construction Summary-Dec-19-2015-Jan-1-2016
Saturday, December 19
- Interior suite work.
- Housekeeping work on site
Monday, December 21
- Interior suite work: drywall and finishing.
- Work on the tower and podium exterior continues.
Tuesday, December 22
- Interior suite work: drywall and finishing.
- Work on the podium exterior continues.
Wednesday, December 23
- Delivery of kitchen appliances.
- Interior suite work: drywall and finishing.
- Work on the tower and podium exterior continues.
Happy Holidays
Thursday, December 24 – Site Closed early for Christmas Eve
Friday, December 25 Site Closed for Christmas
Saturday, December 26 – site scheduled to be closed unless on-site housekeeping work is required.
Sunday, December 27 – Site Closed
Monday, December 28 – Site Closed for Holiday in Lieu of Boxing Day
Tuesday, December 29
- Interior suite work: drywall and finishing.
- Work on the podium exterior continues.
Wednesday, December 30
- Interior suite work: drywall and finishing.
- Work on the podium exterior continues.
Thursday, December 31
- Interior suite work: drywall and finishing.
- Work on the podium exterior continues.
Friday, January 1, 2016 Site Closed for New Year’s Holiday.