Backstage Construction Update – December 19 – January 1, 2016

This is the construction schedule for 1 The Esplanade, Backstage condominium – for December 19, 2015 – January 1, 2016

Exterior work on the podium, suite finishing and on-site housekeeping are the focus of work at Backstage prior over the holidays with the site closed for Christmas, Boxing Day and New Year’s Day and limited activity in between the statutory holidays. This is our final post of 2015. 

Best wishes for the holiday season and Happy New Year. 

Installation of podium insulation at Backstage

Installation of podium insulation at Backstage

Please click on the link to download a printable PDF Summary Construction Schedule for  Dec 19, 2015 – January 1, 2016: Backstage Construction Summary-Dec-19-2015-Jan-1-2016

Saturday, December 19

  • Interior suite work.
  • Housekeeping work on site
Unloading kitchen appliances at Backstage

Unloading kitchen appliances at Backstage

Monday, December 21

  • Interior suite work: drywall and finishing.
  • Work on the tower and podium exterior continues. 

Tuesday, December 22

  • Interior suite work: drywall and finishing.
  • Work on the podium exterior continues. 

Wednesday, December 23

  • Delivery of kitchen appliances
  • Interior suite work: drywall and finishing.
  • Work on the tower and podium exterior continues. 
Backstage podium exterior detail

Backstage podium exterior detail

Happy Holidays 

Thursday, December 24 – Site Closed early for Christmas Eve

Friday, December 25 Site Closed for Christmas

Happy Holidays

Happy Holidays

Saturday, December 26 – site scheduled to be closed unless on-site housekeeping work is required.

Sunday, December 27 – Site Closed

Monday, December 28 – Site Closed for Holiday in Lieu of Boxing Day

Tuesday, December 29

  • Interior suite work: drywall and finishing.
  • Work on the podium exterior continues. 

Wednesday, December 30

  • Interior suite work: drywall and finishing.
  • Work on the podium exterior continues. 

Thursday, December 31

  • Interior suite work: drywall and finishing.
  • Work on the podium exterior continues. 

Friday, January 1, 2016 Site Closed for New Year’s Holiday.

Happy New Year!

Backstage crash wall and tower detail.

Backstage crash wall and tower detail.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: