Backstage Construction Update – December 12 – 18

This a construction update for 1 The Esplanade, Backstage condominium – for December 12 – 18, 2015.

The Hoist (external construction elevator) was removed last week. Work continues on the exterior podium. Suite finishing will continue through the coming weeks. 

Exterior work on the Backstage podium

Exterior work on the Backstage podium

Please click on the link to download a printable PDF Summary Construction Schedule for  Dec 11 – 18: Backstage Construction Summary-Dec-12-18-2015

Saturday December 12

  • Interior suite work.
  • Housekeeping work on site
Elevators ready to use at Backstage

Elevators rough but ready to use at Backstage

Monday December 14

  • Interior suite work: drywall and finishing.
  • Work on the tower and podium exterior continues. 

Tuesday December 15

  • Interior suite work: drywall and finishing.
  • Work on the podium exterior continues. 

Wednesday December 16

  • Delivery of kitchen appliances
  • Interior suite work: drywall and finishing.
  • Work on the tower and podium exterior continues. 

Thursday December 17

  • Interior suite work: drywall and finishing.
  • Work on the tower and podium exterior continues

Friday December 18

  • Interior suite work: drywall and finishing.
  • Work on the tower and podium exterior continues.
Kitchen installation at Backstage

Kitchen installation at Backstage

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: