Backstage Construction Update – December 5 – 11
December 4, 2015 Leave a comment
This a construction update for 1 The Esplanade, Backstage condominium – for December 5 – 11, 2015.
The Hoist (external construction elevator) will be completely removed by Tuesday. Installation of of patio doors and windows in the suites adjacent to the hoist will be completed this coming week. Installation of the insulating membrane on the north and east faces of the podium will continue this coming week. Please check back for updates during the coming week.
Balconies on the SW corner of Backstage