L Tower – December 21, 2015 – January 1, 2016

L Tower construction information 8 The Esplanade – L Tower December 21, 2015 – January 1, 2016.

The exterior tower crane remains up as the construction management team await the delivery of the new derrick that will be used to set the permanent maintenance platform in place at the top of the L Tower. We therefore expect the tower crane to remain in place into January. Over the holidays some move-ins may occur and some ongoing suite finishing work will occur.  This is our final information post of 2015.

We wish you Happy Holidays and a Happy New Year 

St. Lawrence Market Neighbourhood from the L Tower

St. Lawrence Market Neighbourhood from the L Tower

Completed L Tower canopy on The Esplanade

L Tower canopy and sidewalk on The Esplanade

L Tower canopy and sidewalk on The Esplanade

Happy Holidays!

L Tower Christmas Tree

L Tower Christmas Tree

NOTE for L Tower Residents

We get enquires from L Tower residents about the progress of internal work in the building. While we are happy to direct these enquiries to the appropriate people, please note that the purpose of this site is to provide construction information to external neighbourhood stakeholders, particularly in the immediate St. Lawrence Market neighbourhood. 

  • This is our final update L Tower Update for 2015. We wish all visitors to the site a safe and happy New Year. 

 

Backstage Construction Update – December 19 – January 1, 2016

This is the construction schedule for 1 The Esplanade, Backstage condominium – for December 19, 2015 – January 1, 2016

Exterior work on the podium, suite finishing and on-site housekeeping are the focus of work at Backstage prior over the holidays with the site closed for Christmas, Boxing Day and New Year’s Day and limited activity in between the statutory holidays. This is our final post of 2015. 

Best wishes for the holiday season and Happy New Year. 

Installation of podium insulation at Backstage

Installation of podium insulation at Backstage

Please click on the link to download a printable PDF Summary Construction Schedule for  Dec 19, 2015 – January 1, 2016: Backstage Construction Summary-Dec-19-2015-Jan-1-2016

Saturday, December 19

  • Interior suite work.
  • Housekeeping work on site
Unloading kitchen appliances at Backstage

Unloading kitchen appliances at Backstage

Monday, December 21

  • Interior suite work: drywall and finishing.
  • Work on the tower and podium exterior continues. 

Tuesday, December 22

  • Interior suite work: drywall and finishing.
  • Work on the podium exterior continues. 

Wednesday, December 23

  • Delivery of kitchen appliances
  • Interior suite work: drywall and finishing.
  • Work on the tower and podium exterior continues. 
Backstage podium exterior detail

Backstage podium exterior detail

Happy Holidays 

Thursday, December 24 – Site Closed early for Christmas Eve

Friday, December 25 Site Closed for Christmas

Happy Holidays

Happy Holidays

Saturday, December 26 – site scheduled to be closed unless on-site housekeeping work is required.

Sunday, December 27 – Site Closed

Monday, December 28 – Site Closed for Holiday in Lieu of Boxing Day

Tuesday, December 29

  • Interior suite work: drywall and finishing.
  • Work on the podium exterior continues. 

Wednesday, December 30

  • Interior suite work: drywall and finishing.
  • Work on the podium exterior continues. 

Thursday, December 31

  • Interior suite work: drywall and finishing.
  • Work on the podium exterior continues. 

Friday, January 1, 2016 Site Closed for New Year’s Holiday.

Happy New Year!

Backstage crash wall and tower detail.

Backstage crash wall and tower detail.

Backstage Construction Update – December 12 – 18

This a construction update for 1 The Esplanade, Backstage condominium – for December 12 – 18, 2015.

The Hoist (external construction elevator) was removed last week. Work continues on the exterior podium. Suite finishing will continue through the coming weeks. 

Exterior work on the Backstage podium

Exterior work on the Backstage podium

Please click on the link to download a printable PDF Summary Construction Schedule for  Dec 11 – 18: Backstage Construction Summary-Dec-12-18-2015

Saturday December 12

  • Interior suite work.
  • Housekeeping work on site
Elevators ready to use at Backstage

Elevators rough but ready to use at Backstage

Monday December 14

  • Interior suite work: drywall and finishing.
  • Work on the tower and podium exterior continues. 

Tuesday December 15

  • Interior suite work: drywall and finishing.
  • Work on the podium exterior continues. 

Wednesday December 16

  • Delivery of kitchen appliances
  • Interior suite work: drywall and finishing.
  • Work on the tower and podium exterior continues. 

Thursday December 17

  • Interior suite work: drywall and finishing.
  • Work on the tower and podium exterior continues

Friday December 18

  • Interior suite work: drywall and finishing.
  • Work on the tower and podium exterior continues.
Kitchen installation at Backstage

Kitchen installation at Backstage

L Tower – December 12 – 19, 2015

L Tower construction information 8 The Esplanade – L Tower December 12 – 19, 2015.

Finishing work continues on the remaining unoccupied interior suites. Move-ins continue via the Yonge Street service entrance featuring the “turntable” that permits trucks to enter and be turned for ease of unloading and exiting safely back onto Yonge Street. The exterior tower crane remains up and we will have a status update on on Monday, December 21; please check back with us then. 

Completed L Tower canopy on Yonge Street

Completed L Tower canopy on Yonge Street

View ESE from the 56th floor of L Tower

View ESE from the 56th floor of L Tower

Move-ins continue at L Tower via the Yonge Street turntable service entrance.

Move-ins continue at L Tower via the Yonge Street turntable service entrance.

NOTE for L Tower Residents

We get enquires from L Tower residents about the progress of internal work in the building. While we are happy to direct these enquiries to the appropriate people, please note that the purpose of this site is to provide construction information to external neighbourhood stakeholders, particularly in the immediate St. Lawrence Market neighbourhood. 

  •  We post construction information updates weekly on Fridays or more frequently, as information or activity warrants, to keep neighbourhood stakeholders informed, with a particular focus on the immediate St. Lawrence Market neighbourhood

 

 

Backstage Construction Update – December 5 – 11

This a construction update for 1 The Esplanade, Backstage condominium – for December 5 – 11, 2015.

The Hoist (external construction elevator) will be completely removed by Tuesday. Installation of of patio doors and windows in the suites adjacent to the hoist will be completed this coming week. Installation of the insulating membrane on the north and east faces of the podium will continue this coming week. Please check back for updates during the coming week. 

Balconys on the SW corner of Backstage

Balconies on the SW corner of Backstage

Please click on the link to download a printable PDF Summary Construction Schedule for  Dec 5 – 11: Backstage Construction Summary-Dec-5-11-2015

Saturday December 5

  • Interior suite work.
  • Housekeeping work on site
Insulating the podium at Backstage

Insulating the podium at Backstage

Monday December 7

  • Hoist removal (sectional removal of the external construction elevator).
  • Interior suite work: drywall and finishing.
  • Work on the tower and podium exterior continues. 

Tuesday December 8

  • Hoist removal (sectional removal of the external construction elevator).
  • Interior suite work: drywall and finishing.
  • Work on the podium exterior continues. 
  • Pouring concrete stairs on podium by means of a concrete pump.

Wednesday December 9

  • Delivery of limestone cladding for building exterior. 
  • Interior suite work: drywall and finishing.
  • Work on the tower and podium exterior continues. 

Thursday December 10

  • Delivery of limestone cladding for building exterior. 
  • Interior suite work: drywall and finishing.
  • Work on the tower and podium exterior continues

Friday December 11

  • Interior suite work: drywall and finishing.
  • Work on the tower and podium exterior continues.
Putting the insulation on the podium exterior at Backstage

Putting the insulation on the podium exterior at Backstage

Update for L Tower – December 4 – 7, 2015

UPDATE for 8 The Esplanade – L Tower December 4 – 7, 2015.

  • The first section of  temporary derrick at the top of the L Tower was removed successfully this morning, Thursday, December 3. The remaining sections are scheduled to lifted down by the large tower crane on Friday and/or Monday.
Section of the temporary derrick ready to be taken away from L Tower, December 4

Section of the temporary derrick ready to be taken away from L Tower, December 4

  • Barring high winds or inclement weather, the removal of the temporary derrick should be completed on Monday, December 7. We currently expect that the last section of the derrick will be lowered down between 10:00 AM and Noon on Monday.  
  • As sections our lowered, sections of the north sidewalk between Scott Street and Yonge will be temporarily closed to ensure public safety; pedestrians may use the south side of The Esplanade.
Tower crane in use today, Friday and Monday, to lower sections of the temporary derrick from the L Tower Mechanical Penthouse

Tower crane in use today, Friday and Monday, to lower sections of the temporary derrick from the L Tower Mechanical Penthouse

L Tower crane seen from the Mechanical Penthouse.

L Tower crane seen from the Mechanical Penthouse.

NOTE for L Tower Residents

We get enquires from L Tower residents about the progress of internal work in the building. While we are happy to direct these enquiries to the appropriate people, please note that the purpose of this site is to provide construction information to external neighbourhood stakeholders, particularly in the immediate St. Lawrence Market neighbourhood. 

  •  We post construction information updates weekly on Fridays or more frequently, as information or activity warrants, to keep neighbourhood stakeholders informed, with a particular focus on the immediate St. Lawrence Market neighbourhood

 

 

Update for L Tower – December 3, 2015

UPDATE for 8 The Esplanade – L Tower December 3, 2015.

  • The temporary derrick (small crane unit) at the top of the L Tower will be removed starting after 7:00 am Thursday, December 3.
  • The derrick is not functional and needs to be removed. The large tower crane will be used to lower it in sections.
  • As sections our lowered, sections of the north sidewalk between Scott Street and Yonge will be temporarily closed to ensure public safety; pedestrians may use the south side of The Esplanade.
Looking north from the top of the L Tower with the derrick structure that is to be removed from the top of the L Tower beginning December 3

Looking north from the top of the L Tower with the derrick structure that is to be removed from the top of the L Tower beginning December 3

Please click on the link to download a printable PDF Summary Construction Update for Dec 3: L Tower Construction Update-Dec-3-2015

Looking through the temporary derrick set to be removed from the top of the L Tower beginning December 3

Looking through the temporary derrick set to be removed from the top of the L Tower beginning December 3

Crane, Derrick and Ladder. L Tower mechanical penthouse.

Crane, Derrick and Ladder. L Tower mechanical penthouse.

Temporary derrick structure to be removed beginning December 3

Temporary derrick structure to be removed beginning December 3

The top of the L Tower crane seen from the top of the mechanical penthouse.

The top of the L Tower crane seen from the top of the mechanical penthouse.

NOTE for L Tower Residents

We get enquires from L Tower residents about the progress of internal work in the building. While we are happy to direct these enquiries to the appropriate people, please note that the purpose of this site is to provide construction information to external neighbourhood stakeholders, particularly in the immediate St. Lawrence Market neighbourhood. 

  •  We post construction information updates weekly on Fridays or more frequently, as information or activity warrants, to keep neighbourhood stakeholders informed, with a particular focus on the immediate St. Lawrence Market neighbourhood

 

 

%d bloggers like this: