Backstage Construction Update November 28 – December 4
November 27, 2015 Leave a comment
This a construction update for 1 The Esplanade, Backstage condominium – for November 28 – December 4, 2015.
Exterior work at Backstage on the balconies and the podium continues this week and through December. Principle work on the ground floor parking garage should be completed this week. The Hoist (external elevator) will be taken down this coming week. The Hoist will be removed in sections through the building and loaded onto trucks. There will be no deliveries this week.
Please click on the link to download a printable PDF Summary Construction Schedule for November 28 – Dec 4: Backstage Construction Summary-Nov-28-Dec-4-2015
Saturday November 28
- Interior suite work: drywall and finishing.
- Housekeeping work on site
Monday November 30
- Hoist removal (sectional removal of the external construction elevator).
- Interior suite work: drywall and finishing.
- Work on the tower and podium exterior continues.
Tuesday December 1
- Hoist removal (sectional removal of the external construction elevator).
- Interior suite work: drywall and finishing.
- Work on the tower and podium exterior continues.
Wednesday December 2
- Hoist removal (sectional removal of the external construction elevator).
- Interior suite work: drywall and finishing.
- Work on the tower and podium exterior continues.
Thursday December 3
- Hoist removal (sectional removal of the external construction elevator).
- Interior suite work: drywall and finishing.
- Work on the tower and podium exterior continues.
Friday December 4
- Hoist removal (sectional removal of the external construction elevator).
- Interior suite work: drywall and finishing.
- Work on the tower and podium exterior continues.