Backstage Construction Schedule October 17 – 23, 2015

This is the construction schedule for 1 The Esplanade, Backstage condominium – for October 17 – 23, 2015.

Two construction office trailers that are no longer in use will be removed on October 17 from the Yonge Street Railway Bridge. Backstage’s exterior is almost fully glazed, work will continue to complete it over the next few weeks. Soon exterior cladding will be applied to the podium. Work continues to finish the ground floor parking level, along with regular deliveries to the site. 

Please click on the link to download a printable PDF Summary Construction Schedule for October 17 – 23: Backstage & L Tower Construction Summary-October-17-23-2015

Newly installed ground floor windows at Backstage

Newly installed ground floor windows at Backstage

Saturday October 17

  • Interior suite work: drywall and finishing.
  • Construction housekeeping.
  • Removal of two (2) site construction office trailers (pictured below) from the Yonge Street railway bridge, via the train tracks on the south side of the site and then out to Jarvis Street via the alley south of the Toronto Parking Authority Please click here for the Google Earth view.
Trailers to be removed from the railway bridge

Trailers to be removed from the railway bridge, October 17, 2015

Yonge Street Rail Bridge with trailers to be removed October 17

Yonge Street Rail Bridge with trailers that will be removed October 17, 2015

Monday October 19 – ELECTION DAY

  • Interior suite work: drywall and finishing.
  • Window delivery between 8 am and 10 pm 
  • Drywall delivery in the afternoon. 
  • Work on the ground floor parking garage continues. 

Tuesday October 20

  • Interior suite work: drywall and finishing.
  • Drywall delivery in the afternoon. 
  • Work on the ground floor parking garage continues. 

Wednesday October 21

  • Interior suite work: drywall and finishing.
  • Kitchen delivery in the afternoon. 
  • Work on the ground floor parking garage continues. 

Thursday October 22

  • Interior suite work: drywall and finishing.
  • Appliance delivery in the morning. 
  • Work on the ground floor parking garage continues. 

Friday October 23

  • Interior suite work: drywall and finishing.
  • HVAC material delivery in the morning, after 7:00 am.
  • Carpentry material delivery in the afternoon.
  • Work on the ground floor parking garage continues.  
Recently completed Backstage parking level.

Recently completed Backstage parking level.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: