Backstage Construction Schedule October 10 – 16, 2015
October 9, 2015 Leave a comment
This is the construction schedule for 1 The Esplanade, Backstage condominium – for October 10 – 16, 2015.
Backstage’s podium exterior is being covered with an insulating membrane in preparation for the application of the exterior cladding. Work continues on the ground floor parking level, along with regular deliveries to the site. We also note that across the street on the north side of The Esplanade, Toronto Hydro will soon be installing new streetlights.
Please click on the link to download a printable PDF Summary Construction Schedule for October 10 – 16: Backstage & L Tower Construction Summary-October-10-16-2015
Saturday October 10
- Interior suite work: drywall and finishing.
- Construction housekeeping.
Monday October 12 – Thanksgiving Day – Site Closed for the holiday.
Tuesday October 13
- Interior suite work: drywall and finishing.
- Drywall delivery in the afternoon.
- Prep work on the ground floor parking garage continues.
- Podium level membrane installation continues.
Wednesday October 14
- Interior suite work: drywall and finishing.
- Appliance delivery in the afternoon.
- Prep work on the ground floor parking garage continues.
- Podium level exterior membrane installation continues.
Thursday October 15
- Interior suite work: drywall and finishing.
- Prep work on the ground floor parking garage continues.
- Podium level exterior membrane installation continues.
Friday October 16
- HVAC material delivery in the morning after 7:00 am.
- Carpentry material delivery in the morning after 7:00 am.
- Interior suite work: drywall and finishing.
- Prep work on the ground floor parking garage continues.
- Podium level exterior membrane installation continues.