Backstage Construction Schedule October 10 – 16, 2015

This is the construction schedule for 1 The Esplanade, Backstage condominium – for October 10 – 16, 2015.

Backstage’s podium exterior is being covered with an insulating membrane in preparation for the application of the exterior cladding. Work continues on the ground floor parking level, along with regular deliveries to the site. We also note that across the street on the north side of The Esplanade, Toronto Hydro will soon be installing new streetlights. 

Please click on the link to download a printable PDF Summary Construction Schedule for October 10 – 16: Backstage & L Tower Construction Summary-October-10-16-2015 

Backstage and L Tower October 9, 2015

Backstage and L Tower October 9, 2015

Saturday October 10

  • Interior suite work: drywall and finishing.
  • Construction housekeeping.
Elevator doors installed at Backstage

Elevator doors installed at Backstage

Monday October 12 – Thanksgiving Day – Site Closed for the holiday. 

View from the 4th floor parking level at Backstage

View from the 4th floor parking level at Backstage

Tuesday October 13

  • Interior suite work: drywall and finishing.
  • Drywall delivery in the afternoon. 
  • Prep work on the ground floor parking garage continues. 
  • Podium level membrane installation continues.

Wednesday October 14

  • Interior suite work: drywall and finishing.
  • Appliance delivery in the afternoon. 
  • Prep work on the ground floor parking garage continues. 
  • Podium level exterior membrane installation continues.

Thursday October 15

  • Interior suite work: drywall and finishing.
  • Prep work on the ground floor parking garage continues. 
  • Podium level exterior membrane installation continues.

Friday October 16

  • HVAC material delivery in the morning after 7:00 am.
  • Carpentry material delivery in the morning after 7:00 am.
  • Interior suite work: drywall and finishing.
  • Prep work on the ground floor parking garage continues. 
  • Podium level exterior membrane installation continues.

 

Installing the ground floor window frames and canopy at Backstage

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: