Backstage Construction Schedule September 26 – October 2, 2015

This is the construction schedule for 1 The Esplanade, Backstage condominium – for September 26 – October 2, 2015.

Material deliveries and interior suite work are the focus this week at Backstage as more floors get closer to having their suites drywalled, kitchens and washrooms installed. 

Please click on the link to download a printable PDF Summary Construction Schedule for September 26 – October 2: Backstage & L Tower Construction Summary-Sep-26-Oct-2-2015

Saturday September 26

  • Interior suite work: drywall and finishing.
  • Construction housekeeping.
Backstage interior looking west to Union Station

Backstage interior looking west to Union Station

Monday September 28

  • Interior suite work: drywall and finishing.

Tuesday September 29

  • Interior suite work: drywall and finishing.
  • Drywall delivery in the afternoon. 

Wednesday September 30

  • Interior suite work: drywall and finishing.
  • Appliance delivery in the afternoon. 

Thursday October 1

  • Interior suite work: drywall and finishing.

Friday October 2

  • HVAC material delivery in the morning after 7:00 am.
  • Carpentry material delivery in the morning after 7:00 am.
  • Interior suite work: drywall and finishing.

 

Backstage podium deck and swimming pool

Backstage podium deck and swimming pool

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: