Backstage Construction Schedule September 26 – October 2, 2015
September 25, 2015 Leave a comment
This is the construction schedule for 1 The Esplanade, Backstage condominium – for September 26 – October 2, 2015.
Material deliveries and interior suite work are the focus this week at Backstage as more floors get closer to having their suites drywalled, kitchens and washrooms installed.
Please click on the link to download a printable PDF Summary Construction Schedule for September 26 – October 2: Backstage & L Tower Construction Summary-Sep-26-Oct-2-2015
Saturday September 26
- Interior suite work: drywall and finishing.
- Construction housekeeping.
Monday September 28
- Interior suite work: drywall and finishing.
Tuesday September 29
- Interior suite work: drywall and finishing.
- Drywall delivery in the afternoon.
Wednesday September 30
- Interior suite work: drywall and finishing.
- Appliance delivery in the afternoon.
Thursday October 1
- Interior suite work: drywall and finishing.
Friday October 2
- HVAC material delivery in the morning after 7:00 am.
- Carpentry material delivery in the morning after 7:00 am.
- Interior suite work: drywall and finishing.