Backstage Construction Schedule September 19 – 25, 2015

This is the construction schedule for 1 The Esplanade, Backstage condominium – for September 19 – 25, 2015.

REMINDER as posted last week, this Saturday September 19:

  • Resurfacing work will occur on The Esplanade between Yonge Street and the Toronto Parking Authority garage entrance west of Scott Street, along both the south north curbs.
  • NOTE: The north sidewalk along The Esplanade from Scott Street to Yonge Street remains open for pedestrian use.
  • As well the usual interior suite work and construction housekeeping will occur throughout the day from 9:00 am.

Summary Construction Schedule for September 19 – 25: Backstage & L Tower Construction Summary-Sep-19-25-2015

GO Train seen from Backstage condo looking east.

GO Train seen from Backstage condo looking east.

Monday September 21

  • Interior suite work: drywall and finishing.

Tuesday September 22

  • Interior suite work: drywall and finishing.
  • Drywall delivery in the afternoon. 
Yonge Street, Dominion Building and L Tower seen from Backstage.

Yonge Street, Dominion Building and L Tower seen from Backstage.

Wednesday September 23

  • Interior suite work: drywall and finishing.
  • Removing concrete sidewalk in front of Backstage.
  • Appliance delivery for the 10th and 11th floors in the afternoon. 

Thursday September 24

  • Interior suite work: drywall and finishing.

Friday September 25

  • HVAC material delivery in the morning after 7:00 am.
  • Carpentry material delivery in the morning after 7:00 am.
  • Interior suite work: drywall and finishing.

 

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: