Backstage Construction Schedule September 19 – 25, 2015
September 18, 2015 Leave a comment
This is the construction schedule for 1 The Esplanade, Backstage condominium – for September 19 – 25, 2015.
REMINDER as posted last week, this Saturday September 19:
- Resurfacing work will occur on The Esplanade between Yonge Street and the Toronto Parking Authority garage entrance west of Scott Street, along both the south north curbs.
- NOTE: The north sidewalk along The Esplanade from Scott Street to Yonge Street remains open for pedestrian use.
- As well the usual interior suite work and construction housekeeping will occur throughout the day from 9:00 am.
Summary Construction Schedule for September 19 – 25: Backstage & L Tower Construction Summary-Sep-19-25-2015
Monday September 21
- Interior suite work: drywall and finishing.
Tuesday September 22
- Interior suite work: drywall and finishing.
- Drywall delivery in the afternoon.
Wednesday September 23
- Interior suite work: drywall and finishing.
- Removing concrete sidewalk in front of Backstage.
- Appliance delivery for the 10th and 11th floors in the afternoon.
Thursday September 24
- Interior suite work: drywall and finishing.
Friday September 25
- HVAC material delivery in the morning after 7:00 am.
- Carpentry material delivery in the morning after 7:00 am.
- Interior suite work: drywall and finishing.