Backstage Construction Schedule September 5 – 11, 2015

This is the construction schedule for 1 The Esplanade, Backstage condominium – for September 5 -11, 2015.

NOTE: There is a trench dug along the northern perimeter of  the backstage site to permit removal of the remains of the construction caisson wall. 

Trench at Backstage to permit the removal of the remains of the construction caisson wall.

Trench at Backstage to permit the removal of the remains of the construction caisson wall.

Summary Construction Schedule for September 5 – 11: Backstage & L Tower Construction Summary-Sep-5-11-2015
 

Backstage podium deck work September 4

Backstage podium deck with waterproofing layer September 4, 2015


Saturday September 5

  • Interior suite work: drywall and finishing.
  • Construction housekeeping.

Monday September 7 – Labour Day Holiday – SITE CLOSED

Tuesday September 8

  • Interior suite work: drywall and finishing.
  • Tile delivery in the morning after 7:00 am. 
  • Drywall delivery after 12:00 Noon.

Wednesday September 9

  • Interior suite work: drywall and finishing.
  • Appliance delivery in the morning after 7:00 am. 
  • Drywall delivery after 12:00 Noon.

Thursday September 10

  • Interior suite work: drywall and finishing.
  • Kitchen delivery in the morning after 7:00 am. 

Friday September 11

  • Interior suite work: drywall and finishing.
  • HVAC material delivery in the morning after 7:00 am.
  • Carpentry delivery after 12:00 Noon.
Northwest interior Backstage Condominium

Northwest interior Backstage Condominium

 

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: