Backstage Construction Schedule September 5 – 11, 2015
September 4, 2015 Leave a comment
This is the construction schedule for 1 The Esplanade, Backstage condominium – for September 5 -11, 2015.
NOTE: There is a trench dug along the northern perimeter of the backstage site to permit removal of the remains of the construction caisson wall.
Summary Construction Schedule for September 5 – 11: Backstage & L Tower Construction Summary-Sep-5-11-2015
Saturday September 5
- Interior suite work: drywall and finishing.
- Construction housekeeping.
Monday September 7 – Labour Day Holiday – SITE CLOSED
Tuesday September 8
- Interior suite work: drywall and finishing.
- Tile delivery in the morning after 7:00 am.
- Drywall delivery after 12:00 Noon.
Wednesday September 9
- Interior suite work: drywall and finishing.
- Appliance delivery in the morning after 7:00 am.
- Drywall delivery after 12:00 Noon.
Thursday September 10
- Interior suite work: drywall and finishing.
- Kitchen delivery in the morning after 7:00 am.
Friday September 11
- Interior suite work: drywall and finishing.
- HVAC material delivery in the morning after 7:00 am.
- Carpentry delivery after 12:00 Noon.