This is the construction schedule for 1 The Esplanade, Backstage condominium – for September 26 – October 2, 2015.

Material deliveries and interior suite work are the focus this week at Backstage as more floors get closer to having their suites drywalled, kitchens and washrooms installed. 

Please click on the link to download a printable PDF Summary Construction Schedule for September 26 – October 2: Backstage & L Tower Construction Summary-Sep-26-Oct-2-2015

Saturday September 26

  • Interior suite work: drywall and finishing.
  • Construction housekeeping.
Backstage interior looking west to Union Station

Backstage interior looking west to Union Station

Monday September 28

  • Interior suite work: drywall and finishing.

Tuesday September 29

  • Interior suite work: drywall and finishing.
  • Drywall delivery in the afternoon. 

Wednesday September 30

  • Interior suite work: drywall and finishing.
  • Appliance delivery in the afternoon. 

Thursday October 1

  • Interior suite work: drywall and finishing.

Friday October 2

  • HVAC material delivery in the morning after 7:00 am.
  • Carpentry material delivery in the morning after 7:00 am.
  • Interior suite work: drywall and finishing.

 

Backstage podium deck and swimming pool

Backstage podium deck and swimming pool

L Tower September 26 – October 2 2015

8 The Esplanade – L Tower Saturday, September 26 – October 2, 2015.

The external crane at the L Tower (seen below) has one more major job to do, lifting a temporary crane apparatus  to the top of the building. Once there, the temporary crane will be used to put the permanent window washing platform in place. When this work is completed the large tower crane will be taken down. We will be providing updates on this here as information becomes available. 

L Tower Crane on The Esplanade

L Tower Crane on The Esplanade

NOTE for L Tower Residents

We get enquires from L Tower residents about the progress of internal work in the building. While we are happy to direct these enquiries to the appropriate people, please note that the purpose of this site is to provide construction information to external stakeholders, particularly in the immediate St. Lawrence Market neighbourhood. 

L Tower at Yonge and The Esplanade

L Tower at Yonge and The Esplanade

Backstage Construction Schedule September 19 – 25, 2015

This is the construction schedule for 1 The Esplanade, Backstage condominium – for September 19 – 25, 2015.

REMINDER as posted last week, this Saturday September 19:

  • Resurfacing work will occur on The Esplanade between Yonge Street and the Toronto Parking Authority garage entrance west of Scott Street, along both the south north curbs.
  • NOTE: The north sidewalk along The Esplanade from Scott Street to Yonge Street remains open for pedestrian use.
  • As well the usual interior suite work and construction housekeeping will occur throughout the day from 9:00 am.

Summary Construction Schedule for September 19 – 25: Backstage & L Tower Construction Summary-Sep-19-25-2015

GO Train seen from Backstage condo looking east.

GO Train seen from Backstage condo looking east.

Monday September 21

  • Interior suite work: drywall and finishing.

Tuesday September 22

  • Interior suite work: drywall and finishing.
  • Drywall delivery in the afternoon. 
Yonge Street, Dominion Building and L Tower seen from Backstage.

Yonge Street, Dominion Building and L Tower seen from Backstage.

Wednesday September 23

  • Interior suite work: drywall and finishing.
  • Removing concrete sidewalk in front of Backstage.
  • Appliance delivery for the 10th and 11th floors in the afternoon. 

Thursday September 24

  • Interior suite work: drywall and finishing.

Friday September 25

  • HVAC material delivery in the morning after 7:00 am.
  • Carpentry material delivery in the morning after 7:00 am.
  • Interior suite work: drywall and finishing.

 

L Tower September 19 – 25 2015

8 The Esplanade – L Tower Saturday, September 19 – 25, 2015.

Please Note: The north sidewalk along The Esplanade from Yonge to Scott Street will remain open this weekend as asphalt work occurs on south side at Backstage on Saturday, September 19.  – Please click here for more detail.

The Esplanade at L Tower

The Esplanade at L Tower

The external crane at the L Tower (seen below) has one more major job to do, lifting a temporary crane apparatus (pictured below) to the top of the building. Once there, the temporary crane will be used to put the permanent window washing platform in place. When this work is completed the large tower crane will be taken down. We will be providing updates on this here as information becomes available. 

L Tower in Black & White

L Tower in Black & White

NOTE for L Tower Residents

We get enquires from L Tower residents about the progress of internal work in the building. While we are happy to direct these enquiries to the appropriate people, please note that the purpose of this site is to provide construction information to external stakeholders, particularly in the immediate St. Lawrence Market neighbourhood. 

L Tower detail

L Tower detail

 

Backstage Construction Schedule September 12 – 19, 2015

This is the construction schedule for 1 The Esplanade, Backstage condominium – for September 12 – 19, 2015.

NOTE: The trench dug along the northern perimeter of  the backstage site to permit removal of the remains of the construction caisson wall will be filled in on Monday September 14. Nine (9) concrete trucks will provide the required concrete to fill in the trench. The existing concrete sidewalk in front of Backstage will be removed over the course of the next week and replaced on a temporary basis with asphalt. 

Summary Construction Schedule for September 11 – 19: Backstage & L Tower Construction Summary-Sep-12-19-2015

Trench at Backstage that will be filled in with concrete September 14 and 15, 2015

Trench at Backstage that will be filled in with concrete September 14,  2015

Saturday September 12

  • Interior suite work: drywall and finishing.
  • Construction housekeeping.
Kitchen installation at Backstage

Kitchen installation at Backstage

Monday September 14

  • 84 meters of concrete backfill will be delivered by nine (9) concrete trucks to fill in the open trench
  • Interior suite work: drywall and finishing.
  • Removing concrete sidewalk in front of Backstage.
Detail of Trench at Backstage as waterproofing is being applied, September 11. This will be filled in with concrete September 14, 2015

Detail of Trench at Backstage as waterproofing is being applied, September 11. This will be filled in with concrete September 14, 2015

Tuesday September 15

  • Interior suite work: drywall and finishing.
  • Removing concrete sidewalk in front of Backstage.
  • Drywall delivery in the afternoon. 

Wednesday September 16

  • Interior suite work: drywall and finishing.
  • Removing concrete sidewalk in front of Backstage.
  • Appliance delivery for the 10th and 11th floors in the afternoon. 

Thursday September 17

  • Kitchen delivery in the morning after 7:00 am. 
  • Interior suite work: drywall and finishing.
  • Removing concrete sidewalk in front of Backstage.

Friday September 18

  • HVAC material delivery in the morning after 7:00 am.
  • Interior suite work: drywall and finishing.
  • Removing concrete sidewalk in front of Backstage.

Saturday September 19

  • Interior suite work: drywall and finishing.
  • Putting down temporary asphalt to cover the removed sidewalk area.

 

Backstage tower view September 11, 2015

Backstage tower view September 11, 2015

L Tower September 12 – 18 2015

8 The Esplanade – L Tower Saturday, September 12 – 18, 2015.

The external crane at the L Tower (seen below) has one more major job to do, lifting a temporary crane apparatus (pictured below) to the top of the building. Once there, the temporary crane will be used to put the permanent window washing platform in place. When this work is completed the large tower crane will be taken down. We will be providing updates on this here as information becomes available. 

Temporary crane section at L Tower September 11, 2015

Temporary crane section at L Tower September 11, 2015

Temporary crane detail at L Tower September 11, 2015

Temporary crane detail at L Tower September 11, 2015

NOTE for L Tower Residents

We get enquires from L Tower residents about the progress of internal work in the building. While we are happy to direct these enquiries to the appropriate people, please note that the purpose of this site is to provide construction information to external stakeholders, particularly in the immediate St. Lawrence Market neighbourhood. 

As well the north side of The Esplanade will remain open even when and if  there are road closures associated with Backstage construction on the south side of the road. 

The Esplanade north side September 11, 2015

The Esplanade north side September 11, 2015

The L Tower’s large external crane has one more big job to do, raising and lowering the temporary crane to the top of the building. The temporary crane (as noted above) will be used to lift the permanent window washing platform into place. 

L Tower September 11 2015

L Tower September 11 2015

Backstage Construction Schedule September 5 – 11, 2015

This is the construction schedule for 1 The Esplanade, Backstage condominium – for September 5 -11, 2015.

NOTE: There is a trench dug along the northern perimeter of  the backstage site to permit removal of the remains of the construction caisson wall. 

Trench at Backstage to permit the removal of the remains of the construction caisson wall.

Trench at Backstage to permit the removal of the remains of the construction caisson wall.

Summary Construction Schedule for September 5 – 11: Backstage & L Tower Construction Summary-Sep-5-11-2015
 

Backstage podium deck work September 4

Backstage podium deck with waterproofing layer September 4, 2015


Saturday September 5

  • Interior suite work: drywall and finishing.
  • Construction housekeeping.

Monday September 7 – Labour Day Holiday – SITE CLOSED

Tuesday September 8

  • Interior suite work: drywall and finishing.
  • Tile delivery in the morning after 7:00 am. 
  • Drywall delivery after 12:00 Noon.

Wednesday September 9

  • Interior suite work: drywall and finishing.
  • Appliance delivery in the morning after 7:00 am. 
  • Drywall delivery after 12:00 Noon.

Thursday September 10

  • Interior suite work: drywall and finishing.
  • Kitchen delivery in the morning after 7:00 am. 

Friday September 11

  • Interior suite work: drywall and finishing.
  • HVAC material delivery in the morning after 7:00 am.
  • Carpentry delivery after 12:00 Noon.
Northwest interior Backstage Condominium

Northwest interior Backstage Condominium

 

L Tower September 5 – 11 2015

8 The Esplanade – L Tower Saturday, September 5 – 11, 2015.

The long delayed Sony Centre northwest plaza, which the L Tower project provided funds should be underway soon. As we’ve noted before, the plaza designed by Claude Cormier + Associés  (click here for the design page) is the subject of a column by Christopher Hume in yesterday’s Toronto Star (see excerpt below). We look forward to work starting on it this fall transforming the now rather barren site into an exciting public amenity. 

SonyCentrePlaza2

The northwest plaza waiting for its makeover

SonyCentrePlaza

Looking down on the northwest plaza as it is today from the L Tower

NOTE for L Tower Residents

We get enquires from L Tower residents about the progress of internal work in the building. While we are happy to direct these enquiries to the appropriate people, please note that the purpose of this site is to provide construction information to external stakeholders, particularly in the immediate St. Lawrence Market neighbourhood. 

From Thursday, September 3rd’s Toronto Star: 

New plaza at Yonge and Front will offer new ways

In the new Toronto, no space is too small to go unused. The latest example is unfolding on the southeast corner of Front and Yonge where changes now under way will soon bring the busy downtown site into public use. The spot in question isn’t large, but until recently, it didn’t exist. The idea is to… read the whole article at http://www.thestar.com/news/gta/2015/09/03/new-plaza-at-yonge-and-front-will-offer-new-ways.html

%d bloggers like this: