UPDATE August 24, 2015
The partial road closure was off to a successful start this Monday morning. While the eastbound traffic lane from Yonge Street east to the Toronto Parking Authority garage entrance and exit was closed, pedestrian access to Yonge Street was unimpeded along the north sidewalk beside the L Tower and the Sony Centre.
The City of Toronto permits (see links below) for the road closure allow the eastbound traffic lane to be closed from 7:00 am to 7:00 pm daily on weekdays through September 2, every effort will be made to re-open the traffic lane prior to rush hour when feasible.
Please click here for the full construction schedule through Friday, August 28.
You may view or download the Road Closure permits by clicking on the links below:
Permit Access Mast – August 24
Permit Access Mast 8 days – August 25 – September 2

Mobile crane at Backstage, partial road closure, open north sidewalk on The Esplanade to Yonge Street.