Backstage Construction Schedule August 22 – 28, 2015
August 21, 2015 Leave a comment
This the construction schedule for 1 The Esplanade, Backstage condominium – for August 22 – 28, 2015.
NOTE: Please note that temporary crane work and cladding work on the Backstage tower will be occurring from Monday, August 24 through Wednesday September 2.
The road closure will occur only on weekdays and will affect the eastbound traffic lane between Yonge Street and the east entrance to the Toronto Parking Authority garage and the south side pedestrian walkway.
Road closure permits for August 24 and August 25 – September 2: Permit Access Mast – August 24 Permit Access Mast 8 days – August 25 – September 2
Saturday August 22
- Interior suite finishing
- Construction housekeeping
Monday August 24
- Interior suite finishing
- Window delivery for 2nd to 4th floor
- Mobile crane setup at Yonge and Esplanade to erect mast climbing scaffold on west side of Back Stage.
Tuesday August 25
- Interior suite finishing
- Drywall delivery 12 pm to 4 pm
- Mobile crane setup at Yonge and Esplanade to erect mast climbing scaffold on west side of Back Stage.
Wednesday August 26
- Interior suite finishing
- 23rd floor kitchen delivery 8 am to 11 am
- Drywall delivery 12 pm to 4 pm
- Mobile crane setup at Yonge and Esplanade to erect mast climbing scaffold on west side of Back Stage.
Thursday August 27
- Interior suite finishing
- Mobile crane setup at Yonge and Esplanade to erect mast climbing scaffold on west side of Back Stage.
Friday August 28
- Interior suite finishing
- Ventilation material delivery in AM
- Carpentry delivery in AM
- Mobile crane setup at Yonge and Esplanade to erect mast climbing scaffold on west side of Back Stage.

Looking west from the 10th floor of Backstage — also the location of the temporary crane installation August 25 – September 2.