Backstage Construction Schedule August 22 – 28, 2015

This the construction schedule for 1 The Esplanade, Backstage condominium – for August 22 – 28, 2015.

NOTE: Please note that temporary crane work and cladding work on the Backstage tower will be occurring from Monday, August 24 through Wednesday September 2.

The road closure will occur only on weekdays and will affect the eastbound traffic lane between Yonge Street and the east entrance to the Toronto Parking Authority garage and the south side pedestrian walkway.

Pedestrians will have full use of the north sidewalk on The Esplanade from Scott Street to Yonge Street.
Monday August 24 is expected to be a full day closure from 7 am to as late as 7 pm. The balance of the time from August 25 through September 2 it is expected the eastbound traffic lane will be open for the afternoon rush hour.

Road closure permits for August 24 and August 25 – September 2: Permit Access Mast – August 24 Permit Access Mast 8 days – August 25 – September 2
 

Site of August 25 crane installation and road closure on The Esplanade at Yonge.

Site of August 25 crane installation and road closure on The Esplanade at Yonge.


Saturday August 22

  • Interior suite finishing
  • Construction housekeeping
Kitchen installation underway at Backstage

Kitchen installation underway at Backstage

Monday August 24

  • Interior suite finishing
  • Window delivery for 2nd to 4th floor
  • Mobile crane setup at Yonge and Esplanade to erect mast climbing scaffold on west side of Back Stage.

Tuesday August 25

  • Interior suite finishing
  • Drywall delivery 12 pm to 4 pm
  • Mobile crane setup at Yonge and Esplanade to erect mast climbing scaffold on west side of Back Stage.

Wednesday August 26

  • Interior suite finishing
  • 23rd floor kitchen delivery 8 am to 11 am
  • Drywall delivery 12 pm to 4 pm
  • Mobile crane setup at Yonge and Esplanade to erect mast climbing scaffold on west side of Back Stage.

Thursday August 27

  • Interior suite finishing
  • Mobile crane setup at Yonge and Esplanade to erect mast climbing scaffold on west side of Back Stage.

Friday August 28

  • Interior suite finishing
  • Ventilation material delivery in AM
  • Carpentry delivery in AM
  • Mobile crane setup at Yonge and Esplanade to erect mast climbing scaffold on west side of Back Stage.
Looking west from the 10th floor of Backstage -- also the location of the temporary crane installation August 25 - September 2.

Looking west from the 10th floor of Backstage — also the location of the temporary crane installation August 25 – September 2.

 

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: