Backstage Construction Schedule August 15 – 21, 2015

This the construction schedule for 1 The Esplanade, Backstage condominium – for August 15 – 21, 2015.

NOTE: Another quiet week as suite finishing and interior work on the Backstage tower predominate. Material deliveries occur throughout the week but minimal impact on pedestrian and vehicle traffic is expected.  

Click on the link for a downloadable PDF August 15 – 21 Construction Summary: Backstage & L Tower Construction Summary-Aug-15-21-2015

Backstage podium deck looking east, August 14

Backstage podium deck looking east, August 14

Saturday, August 15

  • Interior suite finishing all day.
  • Housekeeping work on-site.
Looking SW from Backstage, August 14

Looking SW from Backstage, August 14

Monday, August 17

  • Interior suite finishing all day.

Tuesday, August 18

  • Interior suite finishing all day. 
  • Drywall delivery from 12:00 pm to 4:00 pm.

Wednesday, August 19

  • Interior suite finishing all day.
  • Kitchen deliveries for interior suites from 8:00 am to 11:00 am.
  • Steel stud deliveries from Noon to 3:00 pm. 

Thursday, August 20

  • Interior suite finishing all day.
  • No scheduled deliveries. 

Friday, August 21

  • Interior suite finishing all day.
  • HVAC and carpentry materials deliveries in the morning.  
Ready for drywall, Backstage construction interior, August 14

Ready for drywall, Backstage construction interior, August 14

 NOTES:

    • There may be some short-term impacts on pedestrian and vehicular traffic flow as delivery trucks are moved into and out of position.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: